Integrated Planner & Master Schedule

Integrated Planner & Master Schedule, Ansaldo STS, Linea 2 Metro Lima

START Date: 
June, 2013

Head of Planning & Cost Control Department

Develop of EPC Master Schedule

Update execution schedule level 3 and 4.

Cost Control (labor and equipment)

Measure Productivity Index (Labor)

Progress Measurement (Engineering, Procurement, Construction and Commissioning)

Curve S Development

Develop Monthly Reports 

Experience Hours (Planning & Scheduling): 
14000
Experience Hours (Cost Management): 
9500
Experience Hours (Forensic Analysis): 
2500

Integrated Planner & Master Schedule , Alstom AJT, 6 x Turbine Retrofits / Mill Replacement / 6 x Boiler Upgrade / 6 x Air Heater upgrades / 6 x Economiser upgrade / Mainsteampipe upgrade

START Date: 
January, 2007
END Date: 
March, 2009

 PROJECT DESCRIPTION (ARNOT CAPACITY INCREASE PROJECT)

Arnot capacity increase project (ACIP), Mpumalanga, South Africa.

Project description The project involves the extensive refurbishment of the Arnot power station in order to meet the increasing demand for power in South Africa.

Arnot has six 350-MW units, making up a total installed capacity of 2 100 MW. The aim is to increase the capacity of each unit to 400 MW, while at the same time extending the station’s lifetime. Value R1,48-billion.