Project Planner, Amey Utilities, West Mains Renewal Lot 1 Batch 3

START Date: 
August, 2017
END Date: 
March, 2018

Contract Project Controller for Amey Utilities’ West Mains Renewal team, scheduling and issuing their Lot 1 Batch 3 programmes for Severn Trent Water, and the County Construction Site Works programmes for the Highways Authority, both to strict monthly timescales.  Assisting with the Mains Renewal programme template and attending County Council Coordination meetings to discuss their Forward Planned roadworks.

Experience Hours (Planning & Scheduling): 
1150