Planning Manager, beard swindon, , Various

START Date: 
August, 2003
END Date: 
August, 2013

Planning Manager with 10 years experience in Construciotn planning, tendering and client monitoring

Business Development Manager / Project Controls Manager, undefined, A variety of oil and gas and EPCC projects

START Date: 
January, 1993

Oil & gas, LNG, Pipeline, water projects.

Estimating, proposals, project management, and Project controls (planning & scheduling, cost eng., doc control, risks).

Business Development Manager / Project Controls Manager, undefined, A variety of oil and gas and EPCC projects

START Date: 
January, 1993

Oil & gas, LNG, Pipeline, water projects.

Estimating, proposals, project management, and Project controls (planning & scheduling, cost eng., doc control, risks).

Senior Scheduler, Burns & McDonnell, McCarthy, Healthcare & Scientific projects,

START Date: 
September, 1985
END Date: 
January, 2013

 

Experience

Burns & McDonnell-St. Louis, MO                                                                     08/2009-01/2013

Senior Scheduler

Planning Engineer, BAE Surface Ships, QEC Aircraft Carriers

START Date: 
March, 2012

Planning Engineer at BAE Surface Ships, Portsmouth dockyard.

Planning the change aspects of the new QEC aircraft carriers encompassing resource, schedule, cost and materials.

Tracking & Scheduling professional , Pemex, Pipeline compression & pumping Oil Stations

START Date: 
August, 2008

Actually working many large projects like Large Compression & Pumping Station ( oil and Gas), Network Pipilines , Storage Facilities, Building access roadways , Bridges and any project related to the Oil Production in Pemex.

Tracking & Scheduling professional , Pemex, Pipeline compression & pumping Oil Stations

START Date: 
August, 2008

Actually working many large projects like Large Compression & Pumping Station ( oil and Gas), Network Pipilines , Storage Facilities, Building access roadways , Bridges and any project related to the Oil Production in Pemex.

Senior Planner, Mansell Construction Services, Numerous Construction Projects From New Stations To Works In Houses Of Parliament

START Date: 
May, 2009
END Date: 
February, 2012

I was planner for the construction and fit out of Hoxton and Haggerston Stations in the North extension of London Overground network.

This included progressing the programmes, issuing early warnings and compensation events to the client and agreeing impact and managing the subcontractor programmes to meet our key dates.

Other projects undertaken while at Mansell include:

Highbury Gardens - Construction of a new residential development on Holloway Road, 2 buildings up to 7 floors.

Construction of a new ticket office at Victoria Underground Station - Tender to

Section Engineer, Sir Alfred McAlpine (botswana Pty), Morupule Power Station

START Date: 
July, 1983
END Date: 
July, 1985

Section Engineer responsible for RC works at Morupule Power Station. Design of concrete mixes and batching plant output control and regulation.

Civil/ Planning Engineer, UEM Builders Berhad, Construction of High-Rise Building

START Date: 
December, 2006
END Date: 
March, 2008
Career started in 2006 as Planning Engineer with UEM Builders Berhad. I was responsible for monitoring and updating the construction progress of high-rise building for UEM Group Head Quarters at KL Sentral. My key role is to assist the Project Manager, Senior Planner and Project team, supervisors and Subcontractor for collating all the physical progress.
Experience Hours (Planning & Scheduling): 
2200
Experience Hours (Cost Management): 
300