Delay Analysis

Controlling and Operations Manager (As a consultant), PMM s.a.r.l, Multiple Projects

START Date: 
February, 2012
END Date: 
August, 2012

Multiple projects, 30 buildings, from 10 to 45 stories, $40 Million total budget.

• Leading the Planning and Quantity Surveying teams.

• Make clients’ site and office visits, and attend progress meetings.

• Create new and revised baseline schedules; follow up the control and updating procedures, and claims.

• Implement new procedures for the department and the company

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Delay Analysts and Senior Planning Consultants, ACC- Matta, Lebanon Water Front City

START Date: 
August, 2014

10 Luxuries Buildings 12 Stories each and a promenade $250 Million Budget.

* Prepare basline schedule.

* Submitt biweekly updates, and reports.

* Prepare delay analysis, and extension of time claims.

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
200

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
Syndicate content