India (AS.IN)

/ Construction Project Planner / Senior Planner, Simplex Infrastructures Limited, Various 2/4/6 laning NationalhIGHWAYS pROJECTS

START Date: 
March, 2011
END Date: 
July, 2012
  • Preparation of fully resource and expense loaded Baseline Construction programme in Microsoft Project 2010 with 15000+ activities.
  • Project management & cost control process, responsible for progress planning & monitoring.
  • Prepared & presented monthly reports to top management in monthly project meetings.
  • Prepared resource optimization report.
  • Provides written updates on critical paths, schedule variances, progress and significant developments for inclusion in both Monthly and Quarterly Reports.
  • Preparation of Delay tables, Productivit
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
250

/ Construction Project Planner / Senior Planner, Larsen & Toubro (L & T) Limited, 000ft2 Office Building

START Date: 
July, 2012
END Date: 
October, 2013
  • Project management & cost control process, responsible for progress planning & monitoring.
  • Provides written updates on critical paths, schedule variances, progress and significant developments for inclusion in both Monthly and Quarterly Reports.
  • Evaluates the impact of changes on cost, schedule, operations and scope documents.
  • Participate in meetings with Project Managers and provide schedule related input.
  • Prepared & developed L2 & 3 Level Baseline construction programme in P6.2 & updating the same on weekly basis.
  • Record and
Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

Sarah Wale

First Name: 
Sarah
Last Name: 
Wale

A passionate blogger and manager and running a website to help project managers for helping them to manage their project effortlessly. 

Professional Since: 
Jun-2015 (4.7 yrs experience)
Years Experience: 
0

S Pandian

First Name: 
S
Last Name: 
Pandian
Oldest experience: 
Sep 1983 (36.4 yrs experience, WARNING: 13.7 years variance with Professional Since)
Years Experience: 
36

PM, Principal Trainer and Cosultant, Velveer, EPC, IT

START Date: 
September, 1983

Engineering graduate with MBA and diploma in SQC & OR  from leading universities and institutions in India having over 3 decades of combined managerial, technical, administrative and training experience in various industry sectors- manufacturing, port operations, air lines, construction, consulting and contracting in India and the Middle East.

PM, Principal Trainer and Cosultant, Velveer, EPC, IT

START Date: 
September, 1983

Engineering graduate with MBA and diploma in SQC & OR  from leading universities and institutions in India having over 3 decades of combined managerial, technical, administrative and training experience in various industry sectors- manufacturing, port operations, air lines, construction, consulting and contracting in India and the Middle East.

Milind Patil

First Name: 
Milind
Last Name: 
Patil

Certified Project Manager (PMI-PMP)

Certified Agile Scrum Master (Exin)

Professional Since: 
Sep-2004 (15.4 yrs experience)
Years Experience: 
0

#planning #projectcontrolsglobal #planning2019 #projectplan #projectplanning, Buildex Engineering CO . W.L.L, & Oil & Gas Projects 2) Buildings 3) Infrastructure

START Date: 
June, 2017
  • Using Primavera P6 / M.S Project for scheduling and reporting of project
  • Understand and comply with tender or contract requirements
  • Set up the WBS (and EPS or OBS where appropriate)
  • Develop the schedule, including resources and costs
  • Set the baseline, Maintain and progress the schedule
  • Report on the time aspects of the project
  • Visualise and report on buff
Experience Hours (Planning & Scheduling): 
18000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
5000

Pavan Kulkarni

First Name: 
Pavan
Last Name: 
Kulkarni
Oldest experience: 
Jun 2017 (2.7 yrs experience, WARNING: 47.4 years variance with Professional Since)
Years Experience: 
49

#planning #projectcontrolsglobal #planning2019 #projectplan #projectplanning, Buildex Engineering CO . W.L.L, & Oil & Gas Projects 2) Buildings 3) Infrastructure

START Date: 
June, 2017
  • Using Primavera P6 / M.S Project for scheduling and reporting of project
  • Understand and comply with tender or contract requirements
  • Set up the WBS (and EPS or OBS where appropriate)
  • Develop the schedule, including resources and costs
  • Set the baseline, Maintain and progress the schedule
  • Report on the time aspects of the project
  • Visualise and report on buff
Experience Hours (Planning & Scheduling): 
18000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
5000

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
Syndicate content