Managing & Senior Consultant, Hill International (Claims), Various

START Date: 
May, 2013
END Date: 
November, 2016

Relocated from Bermuda to the Middle East to specialise in delay analysis initially in the contracts and claims team based at Muscat International Airport. Projects included the following:

Power Plant – Boiler Unit, Kudgi, India

Worked as the delay analyst performing time impact analysis over 21 No. time slices for one of three boiler unit’s extension of time claim. Responsibilities included supervision of a consultant, delay analysis and producing the final report.

Experience Hours (Forensic Analysis): 
7100