Procurement

Senior Site Engineer, MOTA-ENGIL, Sewage Stabilization Ponds

START Date: 
May, 2016
END Date: 
November, 2017

Site Management, Development of Construction Master Schedule, Progress Reports, Assistance on material Procurement

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
500

PROJECT ADMINISTRATOR, ODG PNG Limited, ANGAU Hospital Redelopment Project

START Date: 
May, 2018
  • Project setup initialization kicks start, project and document controls, and procedures, project calendars for meetings, deliveries and major milestones.
  • Preparation of level 2 schedules and schedule basis memorandum, 30 day look ahead schedules.
  • Coordinate with site team to capture daily and weekly targets and discuss deliverables with problem areas/issues to deliver as per budgets hours required.
  • Preparation of O&M and Training Manuals
  • Documetn controls for ODG and Aconex
  • Productivity reports<
Experience Hours (Planning & Scheduling): 
2200
Experience Hours (Cost Management): 
700
Experience Hours (Forensic Analysis): 
100

Planning and Cost Control Engineer, Ozgoren Construction, Various contracts for USAF, US Army, Multi-National Forces, Project and Contracting Office and KBR in Iraq.

START Date: 
August, 2001
END Date: 
February, 2013

Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
1600

Configuration Planner, Material Planner, Planning Engineer, Project Controls Manager, CFW PRECISION METAL COMPONENTS, Aircraft Interior manufacturing

START Date: 
March, 2012

Material Planner: 

  • Analyzed and ordered all required material while utilizing beneficial purchasing techniques (order policies, period orders, etc.) with respect to inventory turns, cost, and lead times.
  • Initiated and implemented facility wide processes which successfully lowered inventory while decreasing shortages on the production floor. Order policies, Period orders, safety stock , etc…

Configuration Planner:

Experience Hours (Planning & Scheduling): 
14000
Experience Hours (Cost Management): 
8000

Business Planning and Development Analyst, PT Prima Layanan Niaga Suku Cadang, -

START Date: 
February, 2018

Business Planning and Development Analyst

- Create and monitoring Company Budgeting

- Make Own Estimate Price for Purchasing Department

Experience Hours (Planning & Scheduling): 
0
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

Technical Director - Risk Management & Project Controls, Melco Resorts & Entertainment, Altira Macau, City of Dreams Macau

START Date: 
July, 2006
END Date: 
December, 2007

Seconded from Steve Tennant Consultancy Ltd to Melco PBL Entertainment Ltd ( now known as Melco Resorts & Entertainment), a Macau casin sub-concessionaire as Technical Director Contracts to head the commercial/contracts aspects of the development of the company's hotel and inegrated gaming resorts in Macau, the USD 524m, 216 key, 6 star Crown Hotel (now known as Altira Macau) and the USD2.6b+, 2,500 key, 6.2m ft2 City of Dreams integrated gaming resort.

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
300

Commercial Manager, Nishimatsu Construction Co. Ltd, Mass Rapid Transit Corporation Contract 107B City Hall Station, Singapore, Mass Rapid Transit Corporation Contract 301 Bugis and Lavender Stations and Tunnels, Singapore, The Hong Kong Electric Co., Ltd

START Date: 
August, 1986
END Date: 
August, 1990

Although still based in Hong Kong with Nishimatsu, my role was expanded to assist with the following contracts in Singapore,  whilst continuing to work on projects in Hong Kong:

Mass Rapid Transit Corporation Contract 107B City Hall Station, Singapore

Design and construction of a major underground railway station with civil defence capability. This cut and cover station experienced a disastrous collapse as excavation was being completed. Significant repair and acceleration costs were recovered by a multi-million dollar insurance claim.

Experience Hours (Cost Management): 
3500
Experience Hours (Forensic Analysis): 
500

PLANNING / PROJECT COORDINATOR, GE POWER CONTROLS, NEW FACTORY FOR GE

START Date: 
June, 2000
END Date: 
November, 2000

PLANNING, DESIGN & ENGINEERING, PROCUREMENT, INSPECTION & SITE SUPERVISION FOR NEW FACTORY CONSTRUCTION WORKS.

Experience Hours (Planning & Scheduling): 
300
Experience Hours (Cost Management): 
200

FIELD ENGINEER, TIC Canada, Epcor Clover Bar

START Date: 
March, 2007
END Date: 
March, 2008

 Project: EPCOR Clover bar Energy-GE LM6000 CTG –Unit I-Power station Installation and  

                                 Commissioning Project.

                                 Planner-Scheduler/Cost Control

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
350

Senior Project Engineer Planning, Kite Arabia Ltd (Jarir Group of Companies), Al Ammariyah Resorts, Jarir Mall, Jarir Book Store

START Date: 
April, 2004
END Date: 
July, 2008

Key Positions Held: 

As Sr. Project Engineer Planning                                        (Jun’07 - Jul’08):

ð  Conducted Periodical Site visits and taken all the necessary actions to meet the client’s requirements.

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Syndicate content