Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Procurement

Planning Estimation, and Cost Control (PECC) Manager , AECOM- Tecsult- Montreal,QC, Canada, DSO Mining Project- Timmins

START Date: 
June, 2011
END Date: 
December, 2011

Planning, Estimation, and Cost Control (PECC) Manager on EPCM Contract for Iron Ore DSO Mining project. Review and validation of Feasibility Study Schedule and CAPEX Budget- re-estimation and rescheduling to develop EPCM presentations accepted by Client. Review of qualifications and cost analysis /comparisons for selection of GMP Contractor. Controls on Process Equipment Procurement and long-lead processes. Development and controls in Proliance-based PMIS system. Development of procedures and systems to be implemented at processing plant site in NE Quebec at New Foundland-Labrador border.

Cost Control Manager, Planning Estimation, AECOM- Tecsult- Montreal, Canada, QC, DSO Mining Project- Timmins

START Date: 
June, 2011
END Date: 
January, 2012

Planning, Estimation, and Cost Control (PECC) Manager on EPCM Contract for Iron Ore DSO Mining project. Review and validation of Feasibility Study Schedule and CAPEX Budget- re-estimation and rescheduling to develop EPCM presentations accepted by Client. Review of qualifications and cost analysis /comparisons for selection of GMP Contractor. Controls on Process Equipment Procurement and long-lead processes. Development and controls in Proliance-based PMIS system. Development of procedures and systems to be implemented at processing plant site in NE Quebec at New Foundland-Labrador border.

EXPEDITING COORDINATOR , SAIPEM SAUDI ARABIA LTD., Manifa Core Hydrocarbon Facilities & Cogeneration

START Date: 
February, 2011
END Date: 
December, 2011

 

 

 

Expediting Coordinator -POSE – Post Order Services

                                    LTA Offshore & Onshore Project, Dammam Port

Managing and coordinating all aspects of designated engagement projects

Employer's Representative , Credit Lyonnais Group (Foncière d’Orient) / Comair Group (JV), “Ellipse” High-Rise Building Project, and renovation of Credit Lyonnais Bank Branches Projects, Beirut, Lebanon.

START Date: 
July, 1992
END Date: 
January, 1994

Duties included preparing an EPC Level 6 schedule of works on PSN6 Project Management software which is similar to Primavera; preparing schedule of demolition works of the old Sursock Castle after dismantling all luxurious accessories; scheduling works for deep excavation on various aggregate site in a busy high-traffic area, then nailing and piling walls; conducting site progress and coordination meetings with subcontractors and construction team to coordinate work sequence with the overall project plan, and assuming follow-up of the consented upon sc

Lead Planner and Buildings Manager, Consolidated Contractors Company CCC / Bechtel (Consortium), Saudi ARAMCO Gas Pipeline Project and SAFCO (Saudi Arabia Fertiliser Co.) 2nd Urea/Ammonia Plant Project - Jubail - Kingdom of Saudi Arabia.

START Date: 
August, 1997
END Date: 
August, 1999

Duties include preparing Primavera schedule of works for all related works detailed to Level 3, loaded with budgeted cost; updating schedule of works on weekly basis together with the status of materials; preparing cost control reports after verification of cost codes, comparing with BOQ prices, checking variations; responsible for quality and procurement of all civil permanent material; guided all architecture and civil shop drawings related to 12,000 m².

Project Controls Manager, Group Five Projects International Ltd, Tonkolili Iron Ore Project

START Date: 
October, 2011
END Date: 
October, 2012

Responsibilities& Achievements:

  • Managed all commercial and Financial activities on the EPCM Project includes Procurement, Contracts,Controls ,Scheduling& Accounts.
  • Projects Planning and Scheduling & Project Reporting: scope management, Project Deliverables, work break down structure, schedule management, forecasting, corrective action, progress measurement/reporting, productivity analysis& calculation.

 

  • Cost Engineering and estimating:Estimating,Cost Management, Cost Control and Forecasting

Planner, Enel Ingeneria e Innovazione S.p.A. , Reftinskaya GRES, Refurbishment of Unit 5

START Date: 
August, 2011

 

1.      Development, and updating  of overall project planning including contractual target comparison and detailed schedule integration for all the phases (engineering, procurement, fabrication, construction and commissioning) with cooperation of the team component;

2.      Coordination with project engineer and engineering team for document issue planning;

Lead Planner, Metronet, LUL Support Additional works

START Date: 
September, 2006
END Date: 
December, 2009

 

2006 – 2007             Lead Project Planner

 

Leading a small team of planners providing detailed fully cost loaded programmes to London Underground (LU), for Metronet Rail Limited (MRL). This was as part of the additional works programme based at Derbyshire house.

Planning & Project Control Manager, KEO INTERNATIONAL CONSULTANTS, SIDRA Medical & Research Centre

START Date: 
June, 2013

Responsible for all planning aspects, programming and progress control of the project, ensure that all project submissions, approvals, procurement, and Milestones are met. Monitoring and following up the project progress, and ensure that all potential delays and risks are addressed and dealt with in appropriate manner.

Liaise with the client and contractor to review and agree the project progress.

Manage micro programmes when required to ensure the delivery of the projects

Project Control Manager, BP/ OMV Petrom, OIL REFINERY PROJECT

START Date: 
May, 1999

2 years Project Contrals Manager in the BP refinery in Rotterdam, Scope 150M to 400M Euro.

Over 3 years Project Controls Manager for OMV/Petrom in Romania scope between 750M and 1.5B Euro.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content