OLE Construction Planning Manager, Balfour Beatty Construction, Crossrail Western Outer Electrification Project

START Date: 
November, 2015
END Date: 
July, 2016

As part of the Cross rail expansion projects, Balfour Beatty is responsible for the Design, Build & Commissioning for a section of OLE (Overhead Line Electrification) track between Stockley Bridge Junction & Maidenhead Station. The works consisted of Foundation Piles for the Signals/Masts & Overhead Line Portal Gantries, All Steel Structure Work, SPS (Small Parts Steel) & Wiring (Including ATF) to accommodate increased traffic through this route.

Experience Hours (Planning & Scheduling): 
1250
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
0

Lead Planner, Metronet, LUL Support Additional works

START Date: 
September, 2006
END Date: 
December, 2009

 

2006 – 2007             Lead Project Planner

 

Leading a small team of planners providing detailed fully cost loaded programmes to London Underground (LU), for Metronet Rail Limited (MRL). This was as part of the additional works programme based at Derbyshire house.