Excavate By Crawler Shovel.

Including excavate and bank/stock pile (m3/hr)              

Sand/Soil        

 

  Machine Bucket -> 0.6m3  0.8m3 1.0m3 1.2m3
Pushed n.e.20 m 20.00 25.00 30.30 35.71
Pushed 20 - 50 m 13.89 20.41 23.81 27.78
Pushed 50 - 125 m  7.63 12.66 16.67 20.41

          

Gravel         

 

Pushed n.e. 20 m 20.40 25.64 31.25 37.04
Pushed 20 - 50 m 14.29 20.83 25.00 28.57
Pushed 50 - 100 m  7.69 12.82 17.24 21.28
  Clay/Chalk/Heavy Soil           
Pushed n.e. 20 m 18.52 23.26 27.78 33.33
Pushed 20 - 50 m 12.66 18.52 21.74 25.64
Pushed 50 - 100 m  6.99 11.63 15.15 18.87
             Boulder Clay           
Pushed n.e. 20 m 16.95 21.28 24.39 30.30
Pushed 20 - 50 m 11.63 16.95 19.61 23.26
Pushed 50 - 100 m  6.33 10.42 13.70 17.54
    Including excavate and load to transport (m3/hr)                  
Machine Bucket -> 0.6m3 0.8m3 1.0m3 1.2m3
Sand/Soil 17.86 23.26 27.03 30.30
Gravel 16.67 23.26 27.78 31.25
Chalk/Heavy Soil 14.71 21.74 25.00 29.41
Boulder Clay 13.70 19.61 22.22 27.03