Primavera

planning and project control manager, Samsung Engineering Co., Shah Gas Development Program & Qatar Fertilise Project

START Date: 
June, 2009
END Date: 
August, 2011

- Cost control, Document control and Schedule control

- Preparing for whole work procedure and report to client

- Developing for EPC master schedule by Primavera

- Developing for EPC baseline schedule by Primavera

- Analysis for EPC master schedule by Risk Management Tools

- Coordination to E, P, C & M

Planning Engineer, Descon Engineering Abu Dhabi, ADGAS

START Date: 
May, 2006
END Date: 
November, 2009

 

Working as a SR. PLANNING ENGINEER with DESCON ENGINNERING ABU DHABI U.A.Esince May 2006 to Oct 2009.

PROJECT DESCRIPTION:

·         ABU DHABI GAS LIQUAFICATION CO (ADGAS) (OFFSHORE) DAS ISLAND, Major Plant Overhaul Train-III, Boiler 5 & 6 - Turnaround 2009

Branch Planner, British Energy / Morson International, Gas Aux & Turbines

START Date: 
November, 2005
END Date: 
July, 2006

Branch Planner then Project Control Lead:
·Creation and Control of Project & Programme Plans (Primavera P3e) with EVA and MIS.
·Liaison with Workpack Managers, Engineering Leads and other Specialists.

CIVIL / PLANNING ENGINEER, QDVC (Qatari Diar Vinci Construction), Underground carparks and utility tunnels

START Date: 
January, 2000

Assisrant Planning Engineer: Project Schedule and Programme; Progress Update; Internal and Client Weekly Reports; Monthly reports

Project Planner, Fluor SA, Engen Refinery epcm

START Date: 
May, 2007
END Date: 
January, 2011

Preparation of level 1 to level 3 EPCM project schedule on the basis of SOW documents with the coordination of different departments and integrating sub contractors schedule into main baseline schedule. Identify defined work activities; verify durations, start dates and end dates meet the project needs. Ensure all deviations are reported. Planning and controlling of multi-disciplinary engineering related projects. Experience in pre-construction (design/tender/PO) and construction stages.  Generating reports on planned vs. actual work. 2 Week look head activities reports.

Project Controls Engineer, Reliance Ports & Terminals Pvt. Ltd., JAmnagar refinery project, Hazira OSBL Integration Project

START Date: 
August, 2007
END Date: 
March, 2011

Responsible for Overall planning & Controlling of project including MIS, Scope Changes.

planning and cost control engineer, Project Management Trainee, Alarko Contracting Group, KIEV / Boryspil State International Airport Development Project

START Date: 
January, 2010

·         Kiev-Boryspil State International Airport Development Project, Contract Price 470,000,000 USD (107,000 m2 terminal building, 200,000 m2 apron, 1.3 km viaduct, 11 passanger boarding bridges)

·         Responsible for planning, scheduling , monitoring and cost control of projects by using primavera project planner and alarko enterprise resource planning software programme.

Lead Planning Engineer, DSRL, Nuclear Decommissioning

START Date: 
August, 2007

Lead Planning Engineer for the Dounreay site on behalf of DSRL.  Ensure compliance in all planning areas to the requirements set by the NDA, critical path analysis, portfolio managemenent and reporting to the client and senior team.  Advise the senior management team on potential savings and way forward.  Run scenarios on funding proposals.  Intelligent customer for the planning software, Primavera.  Write and own the guidance for planning on the site and the rules and tools utilised.

Civil construction planning engineer, Al Futtaim Carillion, AL RAHA DEVELOPMENT

START Date: 
June, 2004

Senior Planning Engineer

 

  • Establishing and preparing the tender program (CL 14) by Co-ordinating with Project Manager/Director.
  • Establishing and preparing the Contract/Baseline/target programme for all projects and continually updates the current work progress to keep the team and management aware of changes to the schedule and possible consequences.
  • Assess & Evaluate Construction Methods & technique.
  • Checking & Approving Subcontractor Programmes.
  • Making of Progress Reports, for Both Management

Senior Engineer, Project Controls, Bateman, Trekkopje Uranium Project

START Date: 
September, 2006
END Date: 
February, 2010

Current Role

  • Plan projects from inception to completion; besides handling construction activities.

 

  • Develop schedule of activities, resource planning, project budgeting; monitor project progress and generate variation report for management.

 

  • Utilize Primavera in the preparation of schedule of activities

 

  • Development of Project Measurement Methodology and Tools for Engineering, Procurement and Construction

 

  •  Progress reporting in term