planning and project control manager, Samsung Engineering Co., Shah Gas Development Program & Qatar Fertilise Project

START Date: 
June, 2009
END Date: 
August, 2011

- Cost control, Document control and Schedule control

- Preparing for whole work procedure and report to client

- Developing for EPC master schedule by Primavera

- Developing for EPC baseline schedule by Primavera

- Analysis for EPC master schedule by Risk Management Tools

- Coordination to E, P, C & M

- Preparing for master file for schedule control (E, P, C & M)

- Preparing for IPS (Interim Payment Schedule)

- Preparing for WBS, CBS, EVM data base

- Updating Engineering, Procurement, Construction, Test and Commissioning schedule

- Updating for master file of cost report

- Engineering Coordination

- Procurement Coordination

- Preparing for Engineering Deliverable Register incl. Vendor document

- Preparing for Procurement Register

- Preparing for Interface Schedule with Other EPC Contractor

- Preparing for Construction Recovery Plan & Mitigation Measure

- Preparing for Daily, Weekly, Biweekly & Monthly Report

                 - Preparing for Feasibility based on drawing & procurement front by Discipline-wise