Budgeting

Principal Consultant, Capability Manager, BMT, Functional Role

START Date: 
August, 2008

Principal Consultant and Capability Manager - BMT

Responsible for the development and delivery of BMT Hi-Q Sigma's Capability Management Strategy and Plan, continuing to ensure that the company has the staff and process needed to meet it's customers needs.

  • Manage annual function planning and budgeting process.
  • Monitor delivery of capability team plans against agreed budget and targets.

In addition, deliver of client focussed tasks for both Government and Industry clients.

Experience Hours (Planning & Scheduling): 
50
Experience Hours (Cost Management): 
50

Drilling Cost Controller, Repsol, Various Drilling Projects On/Offshore Exploratory and Development

START Date: 
October, 2005
END Date: 
October, 2010

Job Duties:

·          Assist in preparing Well Cost Estimate for AFE’s (Authorization for Expenditure). P1 Probabilistic software.

·          Preparation and Implementation of workflow procedure for Cost Control.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
6000

Offshore Cost Controller, TOZZI Kazakhstan Llp / CMS – Caspian Marine Services Kazakhstan, EIT Hook Up Kashagan Project

START Date: 
July, 2011
END Date: 
December, 2012

Job Duties:

·          Fill up daily record sheet (DRS) for manpower under Site/Company Instruction (SI/CI) work.

·          Submit DRS to Client for approval and Payment Application.

Experience Hours (Cost Management): 
1450

Quantity Surveyor, Nishimatsu Construction Co., Ltd, Mass Transit Railway Corporation ~ Contract 408Z Kornhill Advanced Works Contract, Hong Kong , Mass Transit Railway Corporation ~ Contract 414 Sai Wan Ho Station and Tunnels, Hong Kong, Mass Transit Ra

START Date: 
August, 1981
END Date: 
August, 1986

I joined the Hong Kong branch of Nishimatsu Construction Co, Ltd,  one of Japan's largest general contractors, listed on the Tokyo stock exchange as a site-based Quantity Surveyor. 

MTRC Contract 408Z  was an advanced works contract for the Island line. It involved construction to engineer's design of cut and cover tunnels, rock tunnels (approximately 2 km in length), shafts and rock caverns to receive rock crushes and conveyors (by others), site formation, major marine reclamation and seawalls together with elevated and at grade roads.

Experience Hours (Cost Management): 
7000
Experience Hours (Forensic Analysis): 
3000

Lead Project Controller (Cost & Time), Bonatti SpA, DBN2, WI at COVA (ITA), YERP ad Yanbu (KSA), JERP at Jubail (KSA)

START Date: 
January, 2012
END Date: 
June, 2014

Project Planner and Cost Controller for several EPC projects for the O&G industry in KSA and Italy. The roles has included the following duties: budgeting, development of schedules (baselines and progress updates), cost control and cash flow, claim management, reports for the executives.

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
6000
Experience Hours (Forensic Analysis): 
1000

Senior Manager - Planning & Control, Greenko, Paudital Lassa Hydro Power Project

START Date: 
October, 2014
Since Oct ’14 with Greenko Group – Senior Manager (Civil)24 MW Paudital Lassa HEP, Rohru, Shimla District, (HP)Key Deliverables: -
  • Preparation of Detailed Rate Analysis along with Estimates for Infra & Underground works.
  • Construction of Access Road (2.5 Km) to Intake, Adit 1, 1 A, 2 & Power House, completed excavation of Adit 1, 1 A & 2 and reached HRT (5.0 m dia.
Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
5000
Experience Hours (Forensic Analysis): 
200

Senior Project Control Engineer, Anglo American Platinum, Amandelbult Complex, Tumela Projects

START Date: 
January, 2013
END Date: 
September, 2015

Snr. Project Control Engineer – Amandelbult

 

ANGLO AMERICAN PLATINUM– Johannesburg, RSA, ($715 mill.)

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2000

Software Consultant, TEAM Projects & Consultants, Various IT / Software / ERP related Projects

START Date: 
May, 1998
END Date: 
December, 1998

• Data Collection and Users Requirements Analysis
• Software Requirement Specifications
• Data and Information Flow Modeling
• Database Design
• Study, Evaluation and Research of ERP System for Clients 

Project Controls Engineer (Sr. Estimator / QS / Planner), Auckland Steel Pty Ltd, Construction of Various Commercial Building & Residential Building, Hospital, school

START Date: 
April, 2003
END Date: 
September, 2007

• Undertake material take off from Engineering drawings and BOQ.
• Formulate final quote using StruMIS software and provide clients with competitive bid, tender schedule, manning and associated costing structure.
• Set up and monitor budgets associated with estimates submitted across all functions of the company.
• Prepare Master Project Schedules for fabrication and site construction works.
• Monitor and keep track of progress.
• Change Management / Manage all contract variations.

Software Consultant (StruMIS.Net), AceCad Software Ltd, Derby, UK, ERP / MIS Implemetation for Structural Steel Fabricator Companies around the world

START Date: 
September, 2007
END Date: 
December, 2008

• Implement StruMIS.Net system (a steel fabrication management software harnesses work processes through the steelwork contract between departments, suppliers and clients; from estimate tendering, through procurement and production into construction. Project Progress Monitoring and Reporting).
• Prepare software training and installation guides, software specifications and software testing.
• Provide training to AceCad internal and international offices staff.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Syndicate content