Planning Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), various projects

START Date: 
April, 2003
END Date: 
August, 2006

As Planning Engineer I was Responsible for all the Planning and Cost Control aspects of the Projects assigned. I was reporting to the Project Manager and regional Projects Control Manager.

Forensic Planner / Trainer, Marcus Middleton Limited, Various projects

START Date: 
October, 2012

Planning training, planning support, build-up and production of claims, with involvement in programming, analysis of manhours / manpower information and the production of graphical outputs.

Currently working as a consultant with Hargreaves Jones (Commercial and Project Management Services) to supply Planning support to Scottish and Southern Energy on a major £350M NEC3 infrastructure project in Scotland

Consultant, Instituto de Desenvolvimento Gerencial, Various Projects

START Date: 
November, 2001
END Date: 
July, 2008

Instituto de Desenvolvimento Gerencial (http://www.indg.com.br)

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000

Project Planning Leader, GE Oil & Gas, various projects

START Date: 
April, 2013

-     PMO member responsible for Planning discipline and all consecutives reports and control.

Experience Hours (Planning & Scheduling): 
2500

Project Services Manager, Cameron, various projects

START Date: 
October, 2012
END Date: 
March, 2013

-        Ensure adequate resource and competency of personnel in conjunction with the Director of Project Services to operate all Project Services control systems and tools in accordance with contractual requirements and maintaining compliance with the individual project needs.

Experience Hours (Planning & Scheduling): 
1000

Project Planning Supervisor, Cameron, various projects

START Date: 
August, 2011
END Date: 
October, 2012

-        Supervision of a staff composed by 7 Planners, being responsible for analyze trends and reports to Project Managers, assisting the team on the schedules elaboration and monitoring the EPC planning ensuring quality and consistency.

Experience Hours (Planning & Scheduling): 
2300

Industrial Planning Coordinator, Alstom, various projects

START Date: 
October, 2008
END Date: 
May, 2010

-        Coordinating the Operations Planning includes the entire fabrication chain (oxycutting, heavy plate and welding shop, extra heavy machining shop, assembly and test).

-        Management and implementation of Lean Manufacturing procedures, supporting the Manufacturing stage.

Experience Hours (Planning & Scheduling): 
3000

Methods and Process Engineer, Alstom, various projects

START Date: 
October, 2005
END Date: 
October, 2008

Responsible for coordinating and elaborating manufacturing hours estimation for tendering bids. Also developed some tools for welding and machining hour estimation, standardizing for the main components such as spiral cases, rotors, wicket gates, stator frame, spiders, getting wastefulness and using the best practice.

Coordinated workload and guide a staff of 2 Methods and Process Experts.

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
500

Technician Trainee / Tender Assistant / Tender Analyst, Alstom, various projects

START Date: 
October, 1998
END Date: 
August, 2004

Raze and budgets’ costs analysis of equipments which includes material cost, manufacturing hours and methods cost. Responsible to create cash flow and tender master schedules, discussion with vendors, and elaboration of technical and commercial proposals.

Involved on the first SAP implementation in Taubaté Plant as Technician Trainee.

Experience Hours (Planning & Scheduling): 
800
Experience Hours (Cost Management): 
500

Project Engineer, "DPR Construction, Inc.", various projects

START Date: 
April, 2000
END Date: 
April, 2003

Power, Heavy Industrial, Clean Room, Government and Commercial Projects consisting of Claims Avoidance, Procurement, Documentation, Scheduling, Process Development, Construction Supervision and Management.  Responsibilities have included administration, training, scheduling and management of construction projects.  

 

Prana – Las Vegas, NV– Night Club on the Strip

Construction Management - responsible for schedule, contractor coordination, change order implementation, cost controls.

 

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
1500