EVM

Project Planner, Cairnhill Structures Scotland, Pater-Costain-AWE Mensa Project, Reading

START Date: 
March, 2019
END Date: 
July, 2019
  1. Prepared resource loaded Programmes for complex technical projects using MSP and P6
  2. Effectively administered and discharged NEC Contract Programme requirements
  3. Secured Extension of Time claims by demonstrating acceptable excusable delay events in Project Programmes
  4. I improved the quality of Project Programmes by carrying out integrity and quality assessment of Programmes in line with industry standard folling DCMA14
  5. Ensured that project progress updates are submitted on time to clients by providing Site Managers and Proj
Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
300

Lead/Senior Planning Engineer, Bluewater, and different buoy loading/unloading Projects, Bluewater FPSO Modification, Water Technology

START Date: 
June, 2013
END Date: 
September, 2017

-       Review of hand-over documents and develop detailed project schedules and performance baselines

Experience Hours (Planning & Scheduling): 
8200
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

Programme Planning Manager, Industry Client, Type 26 Global Combat Ship

START Date: 
June, 2012
END Date: 
December, 2013

Programme Planning Manager

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
200

Senior Planning Manager - PMO (Dubai Metro and Tram O&M), Transport BU, Serco, Several Rail Transport Projects across Middle East

START Date: 
April, 2015

Initially appointed as the Planning Manager, Program Management Office (PMO) – Dubai Metro and Tram O&M Contract to spearhead the planning, reporting and programme development functions of PMO, later promoted to Senior Planning Manager to lead the planning and reporting activities for ongoing/upcoming rail projects in the Middle East.

 

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
200

Portfolio Planner, Fives Solios, EMAL ALuminium smelter phase 2, ALCAN Kittimat, EMAL LMT

START Date: 
July, 2012
END Date: 
August, 2013

Portfolio Planner

Responsible for developing, maintaining and updating all plans and schedules for different projects (using Primavera P6) and provide analyses on Resources, Risk, Purchasing, Schedule, while controlling the project life cycle. Report progress to the Client and internally for Engineering, Manufacturing, Procurement, Delivery and Installation of equipment.

Experience Hours (Planning & Scheduling): 
2000

Senior Projectcontroller, PM Basics B.V., Several IT projects

START Date: 
September, 2002

Senior Projectcontroller. Specialism: project performance management (earned value management). Project, Program & Portfolio management, PMO, Cost management.

Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
21000

Senior Planning Engineer (PMC), The Louis Berger Group, Warner Bros. Theme Park & Ferrari World Phase II Projects

START Date: 
April, 2015

Senior Planning Engineer (PMC):

 

Experience Hours (Planning & Scheduling): 
1700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
100

PLANNING ENGINEER, HNE Consultants, & Oil & Gas Projects 2) Buildings 3) Infrastructure

START Date: 
June, 2015

 

Planning Engineer

   Preparation of Daily, Weekly & Monthly reports which includes Manpower, Equipment, Material and important activities.

·        Coordinating with different departments like Civil, Architecture, Mechanical and Electrical for close monitoring of Progress & Manpower.

·        Improving Day to Day Project efficiencies by adapting Latest Technologies.

Experience Hours (Planning & Scheduling): 
2800
Experience Hours (Cost Management): 
2800
Experience Hours (Forensic Analysis): 
2000

Estimator and Senior Cost Engineer, JGC Gulf International, Sadara Chemical Complex

START Date: 
May, 2012

A.     Cost Control

Project                :  1. RTIP-Aromatics Unit Sadara (DOW Chemical & Saudi Aramco)

                                (Value $200-MM)

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
4000

Planning Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), various projects

START Date: 
April, 2003
END Date: 
August, 2006

As Planning Engineer I was Responsible for all the Planning and Cost Control aspects of the Projects assigned. I was reporting to the Project Manager and regional Projects Control Manager.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Syndicate content