Ground Trench Excavation Strut Rates

Ground Trench Excavation / Strut Rates (m2/hr)

 Trench width not exceeding 2.0 m wide         

 

  Trench Depth --> Ne1.5m 1.5-3m 3-4.5m
Single horiz boards Fix Strike 16.7 33.3 - - - -
Double horiz boards Fix Strike 7.7 16.7 7.7 14.3 - -
Single strut vert boards Fix Strike 14.3 33.3 - - - -
Close Boards,with whaling Fix Strike 4.5 9.1 4.2 8.3 4.0 8.0
  Trench width exceeding 2.0m wide                             

 

  Trench Depth Ne1.5m 1.5-3m 3-4.5m
Single horiz boards Fix Strike 5.6 11.1 5.3 10.0 - -
Double horiz boards Fix Strike 7.1 14.3 7.1 14.3 - -
Single strut vert boards Fix Strike 5.9 112.5 5.6 11.1 5.3 10.0
Close Boards, with whaling Fix Strike 7.1 14.3 6.7 1.3 6.7 12.5

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.