Lift Erection Schedule

Please find below the sequence or erection of a Lift..:

1. Site Survey of Lift Shaft
2. Installation of Rails
3. Installation of Door Frames
4. Installation of Outside Doors, Indicators and push buttons
5. Assembly of Cabin
6. Installation of Motor
7. Main Cable Installation, Connection to BMS if applicable.
8. Testing
9. Complete Installation of Interior Finishes
10. Balancing and Commissioning

These are the basic steps, other requirements will apply per specifications.
 

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes