Project Planning, Scheduling, Control and Monitoring involved in various projects., M-IO Builders Sdn Bhd, Al Bidda Platinum Tower; Al Hitmi Office Building; Dubai Metro Stations

START Date: 
September, 2006
END Date: 
September, 2009

Job Description:

A.     Project planning, scheduling, control and monitoring involved in various projects such as:

A.1. M-IO Builders Qatar W.L.L.
Doha, Qatar

- Al Bidda Platinum Tower
2,300 MT of Structural Steel Fabrication, Erection,
Painting and Fire Proofing.

- Al Hitmi Office Building
1,700 MT of Structural Steel Fabrication, Erection,
Painting and Fire Proofing.
     
- Dubai Tower (Tender Document Preparation)

Senior Project Controls Engineer, Arabian Bemco, PP-10 2000MW Simple Cycle Power Plant, Qassim 1000 MW Simple Cycle Power Plant, Qurayyah 3000 MW Combined Cycle Power Plant

START Date: 
February, 2006
END Date: 
June, 2011

Planning, Scheduling, Resource Loading, Progress Reporting, Claims, Cost Control, Contract Administration, Document Management, Training.

Assistant Planner or Planning Engineer, Khansaheb Civil Engineering LLC (In association with Interserve Plc UK), Dubai, Mirdiff Commercial Development

START Date: 
June, 2015

Planning Engineer - Khansaheb Civil Engineering LLC

Preparation of clause 14 resource & cost loaded construction program in line with contract conditions.

Progress Monitoring & Updating schedules, computing variance & suggeting remedial actions.

Generate & Update Earned Value project coontrols curves & reports.

Correspondence to client, consultant & contractors relevant to schedule in accordance with conditions of contract.

Preparation of progress reports (weekly, monthly & daily), weekly look ahead schdules & KPIs.

Experience Hours (Planning & Scheduling): 
1700
Experience Hours (Cost Management): 
1700
Experience Hours (Forensic Analysis): 
1700

Planning and Scheduling Engineer, United Construction Company, Palm Galleria

START Date: 
June, 2008
END Date: 
August, 2009

-         Preparation of baseline schedules & respective cash flow & resources requirements.

-         Conducting trend analysis and path forecasting along with all periodic reports, S-curve, & Manpower Histogram

-         Handling claims and delay analysis in accordance with the Conditions of Contract

Senior Scheduler / Planner, Sama Contracting, The Lagoons

START Date: 
September, 2008
END Date: 
May, 2009

Project : : The Lagoons : Al Laylak Towers
Client : : Sama Dubai (member company and subsidiary of Dubai Holding)

Project Planner, Fluor SA, Engen Refinery epcm

START Date: 
May, 2007
END Date: 
January, 2011

Preparation of level 1 to level 3 EPCM project schedule on the basis of SOW documents with the coordination of different departments and integrating sub contractors schedule into main baseline schedule. Identify defined work activities; verify durations, start dates and end dates meet the project needs. Ensure all deviations are reported. Planning and controlling of multi-disciplinary engineering related projects. Experience in pre-construction (design/tender/PO) and construction stages.  Generating reports on planned vs. actual work. 2 Week look head activities reports.

Seniot Project Control Engineer, Petronas, PFK Project, Ampa Fairley Rationalization Project, Thar Jath Development Project

START Date: 
April, 1995
END Date: 
May, 2008
Responsibilities included providing capital project support featuring leadership, expertise and tools for project goals and deliveries, project management, risk assessment, technical and feasibility studies, work-scoping and engineering studies for the research and technologies division of the international corporation.
Experience Hours (Planning & Scheduling): 
28000
Experience Hours (Cost Management): 
5000
Experience Hours (Forensic Analysis): 
100

planning and cost control engineer, Project Management Trainee, Alarko Contracting Group, KIEV / Boryspil State International Airport Development Project

START Date: 
January, 2010

·         Kiev-Boryspil State International Airport Development Project, Contract Price 470,000,000 USD (107,000 m2 terminal building, 200,000 m2 apron, 1.3 km viaduct, 11 passanger boarding bridges)

·         Responsible for planning, scheduling , monitoring and cost control of projects by using primavera project planner and alarko enterprise resource planning software programme.

Sr.Project Controls Engineer, Bechtel, BSII, Cooperative Biological Engagement Program (CBEP)

START Date: 
January, 2002

Performed Project Controls Engineer duties as required by Country Manager and Project Manager

Experience Hours (Planning & Scheduling): 
16500
Experience Hours (Cost Management): 
8500