Clay, Quarry Tiles

 

·         Typically carried out with a 3 man gang, bedded in cement and sand base

 

Floor Areas 

 

Small areas much cutting 0.8 m2/hr
Large areas little cutting 2.2 m2/hr

 

Window Cills etc 

 

Fixing, level line edge batten 55.5 m/hr
Fixing tiles, clean and grout 1.56 m2/hr