Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

scheduling

Management Consultant, Ernst & Young, RESTRICTED

START Date: 
November, 2016

Manager, Advisory, Program Management

Provding asset owner operators with end to end advice on the capital project lifecycle

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
250

Sr. Planning Engineer & Quantity Surveyor, TOA Corporation, Kuwait Naval Base - Breakwater and Cargo Pier Repair Project

START Date: 
February, 2017
END Date: 
November, 2018
  • In charge of the preparation of a baseline network analysis programme complete with resource loading. 
  • Recording and reporting the actual progress of the work versus the planned work in P6 and RMS 3.0 system.
  • Monitoring all activities in the project schedule for potential delays, and regularly update claims and variation logs.
  • Prepare the 3 weeks look-ahead schedule for weekly coordination meeting
  • Prepare the monthly progress report and the monthly interim progress payment.
  • Prepare the Time Impact Analysis and other necessary substantiation

Project Planner, Cairnhill Structures Scotland, Pater-Costain-AWE Mensa Project, Reading

START Date: 
March, 2019
END Date: 
July, 2019
  1. Prepared resource loaded Programmes for complex technical projects using MSP and P6
  2. Effectively administered and discharged NEC Contract Programme requirements
  3. Secured Extension of Time claims by demonstrating acceptable excusable delay events in Project Programmes
  4. I improved the quality of Project Programmes by carrying out integrity and quality assessment of Programmes in line with industry standard folling DCMA14
  5. Ensured that project progress updates are submitted on time to clients by providing Site Managers and Proj
Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
300

Project Controls Manager, PNW LNG, PNW LNG

START Date: 
November, 2015
END Date: 
September, 2017

Responsibilities include leading Project Controls team responsible for monitoring and performing surveillance of project controls for planning, scheduling, progress performance, change order management, budgeting and cost controls. Manages documentation and deliverables from EPCC Contractors,  database including EDMS.

Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
500

Project Controls Manager, PNW LNG, PNW LNG

START Date: 
November, 2015
END Date: 
September, 2017

Responsibilities include leading Project Controls team responsible for monitoring and performing surveillance of project controls for planning, scheduling, progress performance, change order management, budgeting and cost controls. Manages documentation and deliverables from EPCC Contractors,  database including EDMS.

Principle Project Controls Specialist, Jacobs Canada, Well Pad Program for SUNCOR

START Date: 
September, 2012
END Date: 
March, 2015

Responsibilities included recommendations for planning and scheduling as well as monitoring engineering cost requirements. Project planning and supervision of major projects including budget and timelines. Conducted quantitative and qualitative risk analysis.

Experience Hours (Planning & Scheduling): 
8000

Senior Project Controls /Planning Engineer, SABIC PMT, YANSAB- SABIC

START Date: 
May, 2008
END Date: 
July, 2012

Responsibilities included designing logical schedules for new projects, creating monitoring tools and analysis. Additionally, integrated pre-commissioning and commissioning of eight petrochemical facilities.

  • Monitored coordination of commissioning activities between facilities.
  • Ensured start-up activities adhered to flawless start-up methodologies
  • Ensured compliance with local standards and regulations
  • Delivered timely progress, quality assurance and budget reports
Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
4000

Senior Project Controls /Planning Engineer, SABIC PMT, YANSAB- SABIC

START Date: 
May, 2008
END Date: 
July, 2012

Responsibilities included designing logical schedules for new projects, creating monitoring tools and analysis. Additionally, integrated pre-commissioning and commissioning of eight petrochemical facilities.

  • Monitored coordination of commissioning activities between facilities.
  • Ensured start-up activities adhered to flawless start-up methodologies
  • Ensured compliance with local standards and regulations
  • Delivered timely progress, quality assurance and budget reports
Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
4000

Project control manager, Air Products Plc, Air Separation Units, Petrochemicals

START Date: 
April, 2018

Project Control Manager: Handling multile projects with a team of cost and planning professionals

Experience Hours (Planning & Scheduling): 
850
Experience Hours (Cost Management): 
850
Experience Hours (Forensic Analysis): 
850

Project control Manager, Reliance Industries Limited, J3 Reliance

START Date: 
January, 2013
END Date: 
April, 2018

Senior Manager Project control:

  1. Team handling
  2. Mupltiple projects managed 
  3. Project handeled: Refinery Off Gas Cracker, MEG, LDPE, LLDPE, PTA,PET
  4. Developed and maintain schedule in P6
  5. Critical path, delay analysis and EVM analysis
  6. Change Management
  7. Budget control and budget monitoring
  8. Variance analysis
  9. Automation in cost reporting and progress reporting system
  10. Database and cost bechmarking
  11. Cost estimation (class 3,4)
  12. ASPEN tech cost evaluation 
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
5500
Experience Hours (Forensic Analysis): 
1000

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content