Sr. Planning Engineer & Quantity Surveyor, TOA Corporation, Kuwait Naval Base - Breakwater and Cargo Pier Repair Project
START Date:
February, 2017
END Date:
November, 2018 - In charge of the preparation of a baseline network analysis programme complete with resource loading.
- Recording and reporting the actual progress of the work versus the planned work in P6 and RMS 3.0 system.
- Monitoring all activities in the project schedule for potential delays, and regularly update claims and variation logs.
- Prepare the 3 weeks look-ahead schedule for weekly coordination meeting
- Prepare the monthly progress report and the monthly interim progress payment.
- Prepare the Time Impact Analysis and other necessary substantiation documents on each delaying event for submission to the Client.
- Prepare monthly pay request/ invoices for client submission and approval.
- Coordinate regularly to all engineers in order to establish the program updates, progress reports, identify site issues and make recommendations.
- Advising the Project Manager of any potential delays to the program, and work closely with the project team to develop mitigations to minimize or avoid these delays.
- Monitoring production rates and compare with planned.
- Closely coordinate with the Client and attends Client Meetings if required.
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: