Primavera P6

Planning Engineer, Radient Hitech Engineers, HPCL Mumbai TA 2015

START Date: 
March, 2015
END Date: 
August, 2015

Turnaround Planning, Scheduling, Baselining, Progress Updates, and Reporting, Daily reporting to the client, attend the related meetings, give suggestions, explain queries, site visit for ensuring the safety and quality of the activities.

Experience Hours (Planning & Scheduling): 
1900
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
400

Senior Project Planner, ESKOM, Kusile Power Station Project

START Date: 
November, 2015
  • Update project dashboard with various- Earned value, Burn rate, resource allocations, Key Milestones on weekly basis
  • Analyse and manitain all reported project activities, emphazing items such as slipped tasks, variance, scope variations and upcoming tasks.
  • Educate and advise project teams on various project management processes.
  • Collaborate with project team to ensure schedule are accurate and changes and impact are accurately reflected in the schedule.
  • Identified and managed critical activities that might put the kep milestones at risk if they slipped.<
Experience Hours (Planning & Scheduling): 
1800

Planning Engineer, Techno Engineering & Associates, Marmaray CR-3 Project

START Date: 
June, 2016

Planning Engineer Techno Engineering & Associates 

Updating programs of work for individual projects using Primavera P6;• Assisting in the preparation of Project Budget & Calculation of detailed man-hours, machine hours;• Resource Loading in Primavera P6 for individual Projects;• Preparation of project Cash flow;• Establishing the project Critical Path;• Preparation of man power Calculation & utilization schedule
Experience Hours (Planning & Scheduling): 
1650

Engineer Planning (Civil) , Galfar Al Misnad Engg & contracting WLL, Extension of Al Jazeera Satellite Network Building, Doha

START Date: 
March, 2011
END Date: 
April, 2012

Planning & monitoring of construction activities for commercial & industrial projects through planning software Primavera-6. Internal project cost control through SAP. Project planning and monitoring pre-cast RCC

Experience Hours (Planning & Scheduling): 
650
Experience Hours (Cost Management): 
650
Experience Hours (Forensic Analysis): 
650

Planning Engineer, Chicago Maintenance & Construction Co. L.L.C., GEMS Nations Academy School Al Barsha Dubai

START Date: 
September, 2015

Planning & monitoring of construction activities of 4 Lac sq. ft. high profile school building in Dubai.

Experience Hours (Planning & Scheduling): 
1250
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
150

District Scheduling Manager, PCL Constructors, District Scheduling Manager

START Date: 
July, 2005

I have vast scheduling experience on many complex and accelerated/compressed schedules.  I have more than 10 years of construction experience in construction, engineering, and project scheduling.  I have effectively led teams in the field, communicated with owners, engineers, subcontractors, and suppliers to accurately prepare work that is the greatest value to the client.  I have a well-rounded construction background encompassing a broad range of roadway and bridge projects that enable me to draw upon my field experience to provide an effective and efficient schedule. 

Experience Hours (Planning & Scheduling): 
22100
Experience Hours (Forensic Analysis): 
3000

Site Planning Engineer, Atkins Faithful & Gould, New King Abdulaziz International Airport Development Project

START Date: 
August, 2011
END Date: 
May, 2015

·        Preparation of a comprehensive cost and resource loaded contract baseline time schedule for the Aprons, Taxiways, Load Centers, Airside Storm water network (Pipe and box culverts), Blue Water Network, Airfield Ground Lighting network and the associated Vault Rooms, Glycol Network, 400Hz Network, Fuel Hydrant Network from the Fuel Farm, Fuel supply network from Aramco depot, GSE Tunnel/Ramps and security checkpoints, by reading the design drawings (70%).

Planner & Scheduler, PETROLEUM MECHANICAL EXECUTING & ASSMEBLY JSC, 12/9 OIL AND GAS CEMENT PLANT PROJECT

START Date: 
September, 2009
END Date: 
September, 2010

Ü   12/9 OIL AND GAS CEMENT PLANT PROJECT.

Position: PLANNER/ PROJECT ENGINEER

Description of Project:

·        Investor: Petro Vietnam Nghe An Cement JSC.

·        Places: Hội Sơn - Anh Sơn - Nghệ An

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000

Senior Scheduler/ Schedule Analysit, HNTB Corp, Florida High Speed Rail

START Date: 
December, 2009
END Date: 
February, 2011

Assisted in the development of program management procedures and protocols.  Developed and maintained schedule for design and right-of-way for the high speed rail proposed between Orlando and Tampa.

Experience Hours (Planning & Scheduling): 
2200
Experience Hours (Cost Management): 
300

Lead Planning & scheduler, YURA S.A., MISTI Project

START Date: 
February, 2013

YURA S.A. Lead Planning & Scheduler 

Perform planning and control of project of the company

Perform planifiaccion , monitoring and control of projects of the company
Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
2000