Creation of new planning system using MS Project.  Requirements capture to determine user needs.  Development of individual project schedule templates.  Integration of all projects schedules into overview.  Use of resource pool to manage resource requirements and carry out capacity planning.  Development of system to provide look ahead.  Provision of MS Project training.

Experience Hours (Planning & Scheduling): 
3400

Senior Planner, Glencorrie Consulting Limited, Expro North Sea Limited

START Date: 
October, 2003
END Date: 
January, 2011

Project planning with MS Project.  Development of integrated planning system to assist with project controls.  Implementation of Primavera P6 system.  Design and development of Methodology Manager to ensure consistency accross project creation.  Implementation of Primavera web based system.  Responsible for upgrades to Primavera  system including server software.  System manager for Primavera system.  Design develpment and on-going support for Primavera P6 V8.  Provision of training for Primavera users.

Experience Hours (Planning & Scheduling): 
15500
Experience Hours (Cost Management): 
1000

Senior Planner, Scom, Lynx TLMP

START Date: 
May, 2003
END Date: 
October, 2003

Carried out a project planning and coordination role for the Lynx Integrated Project Team. The team required a Through Life Management Plan.  This was achieved through user requirements, data-gathering and gap analysis.  A fully functional, integrated database was produced using Access and web-bsed software tools.

Experience Hours (Planning & Scheduling): 
800

Senior Planner, Mott MacDonald, Simandou Iron Ore Mines and infrastructure

START Date: 
June, 2014

Project Description:

Multi-billion dollar project to build two new iron ore mines in Guinea, plus associated rail and port infrastructure.

 

Roles and Responsibilities:

Senior Planner within a 5-strong team acting on behalf of the client during the tender phase. My main focus of work was on the rail element of works (approx 670km single track, including approx 30km of tunnels)

Responsibilities include: 

Prepare ITT documentation

Assess Tender returns

Experience Hours (Planning & Scheduling): 
350

senior planner, Fluor, & Oil & Gas Projects

START Date: 
January, 1994

 

 

Job Profile – Key Roles & Responsibilities

 

 

 

·Defining and identifying Work Breakdown Structures (WBS) and understanding the scope of work and scope of services in the Contract.

 

·Responsible for Supervising Planners and Technicians assigned to Projects.

 

·Produce different levels of schedules

Experience Hours (Planning & Scheduling): 
13000
Experience Hours (Cost Management): 
13000
Experience Hours (Forensic Analysis): 
13000

senior planner, Fluor, & Oil & Gas Projects

START Date: 
January, 1994

 

 

Job Profile – Key Roles & Responsibilities

 

 

 

·Defining and identifying Work Breakdown Structures (WBS) and understanding the scope of work and scope of services in the Contract.

 

·Responsible for Supervising Planners and Technicians assigned to Projects.

 

·Produce different levels of schedules

Experience Hours (Planning & Scheduling): 
13000
Experience Hours (Cost Management): 
13000
Experience Hours (Forensic Analysis): 
13000

Senior Planner, Siemens S.A.E., Nile Ritz Carlton Hotel

START Date: 
April, 2008

Current Job:

Jobtitle:Senior Planning Engineer

Employer:Siemens Technologies S.A.E.

From:April 2008

Job description:

  • Preparing & updating time schedules for MEP works using Primavera Project Planner 3 & 6 and Microsoft project.
  • Preparing monthly reports.
  • Preparing claims for time extensions.
  • Preparing Progress payments for MEP works.
  • Preparing variation orders.

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
12000

Senior Planner, Keepmoat (Bramall) Construction, Care Homes, remodeling - £10million. = Aylesbury

START Date: 
April, 2011
END Date: 
July, 2013

Pre contract - Produce tender, cost plan, design programmes, fire and traffic management  and phased / feasibility construction plans. To attend and make the presentation at settlement and pre-settlement meetings to the board, highlighting complexity of build, labour, plant, risks and durations. To attend and present at client interviews.

Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
1200
Experience Hours (Forensic Analysis): 
50

Senior Planner, Mott MacDonald, Heathrow Q5

START Date: 
February, 2014
END Date: 
May, 2014

Project Description

MSP services to BAA for managing 5-year programme of capital works at Heathrow Airport, UK.

 

Role & Responsibilities

Lead Planner on behalf of BAA for a number of projects within their "Portfolio of Projects" sub-programme.

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
350
Experience Hours (Forensic Analysis): 
250

Senior Planner, Mott MacDonald, Essex Waste MBT

START Date: 
December, 2013
END Date: 
January, 2014

Project Description

New build Mechanical & Biological Treatment (MBT) plant to process circa 500k tonnes of household waste in Essex, UK.

 

Role and Responsibilities

Experience Hours (Planning & Scheduling): 
300