Planning and Scheduling Manager, CLM Delivery Partner, London 2012

START Date: 
February, 2007
END Date: 
February, 2012

Planning and Scheduling Manager working on Venues of the 2012 Olympic Park.

I was responsible for administration of the Programme for the Olympic Stadium and the Aquatics Centre.  This included managing the programme for the NEC, reporting performance from the contractors programmes running risk analysis of the programmes and integration with other projects on the Olympic Park.

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
2000

Senior Planning Engineer, Vinci Construction UK Limited, London Underground Various

START Date: 
January, 2010

Senior Planner for successful Baker Street S8 Upgrade including hr by hr possession planning. Experience in setting up/supervising numerous weekend possessions. Current Senior Planner for structures & civils at Victoria Station Upgrade.

Senior Planning & Schedule Engineer, PT. Punj Lloyd Indonesia, 2x30MW Coal Fired Power Plant, Tanjung, Tabalong – Kalimantan Selatan, Indonesia.

START Date: 
November, 2009
END Date: 
April, 2010
  1. Create, maintain and updating Master Schedule (using Primavera Version 5).
  2. Create Two Weeks Look Ahead Schedule in level 5.
  3. Review Sub-Contractor schedule and progress and ensure the progress of Sub-Contractor is correct.
  4. CPM analysis.
  5. Oversee any possible delay of work and prepare catch up plan.
  6. Studied the possibilities of delays in the work and proposed solutions to overcome these delays.
  7. Plan allocation of labor and equipment and compare with actual conditions in the site.
  8. Make a budget plan using Primavera P5

Lead Planner, AMEC Power & Process Europe, Hole House Underground Gas Storage Phase 3

START Date: 
September, 2011
END Date: 
August, 2012

Lead planner on underground gas storage EPC project for key client EDF Energy.

Responsibilities include maintenance of Project Programme in Primavera P6, Supervision of the Progress Measurement database and Earned Value reporting.

Consultant - Project Controls, EC Harris, Post T5 Transfer Baggage System

START Date: 
April, 2008
END Date: 
May, 2009

PCM for a baggage system project at Heathrow involving construction of a 2km tunnel and subsequent fit-out with baggage system

Planning Engineer, Vinci Construction UK Limited, London Underground Various

START Date: 
December, 2007
END Date: 
December, 2009

Tender planner for successful Tottenham Court Road Station Upgrade, Baker Street S8 Enabling, Warren Street CMS bids, tender planner for LU SSR Power Upgrade Bid.

Market Place