Project Controls Lead, Transport for London (Track Partnership), London Underground Infrastructural Renew Programme

START Date: 
August, 2014
END Date: 
March, 2017

Responsible for the construction delivery Planning of Ballast Track Replacement (BTR) and Points & Crossings (P&C) Projects according to the End to End (T-Minus) Process from a work bank of projects in Primavera P6 and weekend possession works using the approved output rate to produce Time Chainage & Primavera P6 programme. Preparation of the Train Matrix by calculating the volume of spoils and materials each train can bring & take out of site during the possession.

Experience Hours (Planning & Scheduling): 
6250
Experience Hours (Cost Management): 
6250

Project Control Lead - Sr Planner/Scheduler, worleyparsons Canada, Mix of Projects - Edmonton - FortMcmurray - Calgary

START Date: 
January, 2010
END Date: 
July, 2014

Project Control Lead

Sr Planning/ Scheduling Engineer

Worley Parsons – (Edmonton/ RedWater/FortMcmurray) – Alberta – Canada 

March 2013– July2014

 

NORTH WEST REDWATER PARTNERSHIP NWR    – (Edmonton/ REDWATER) – Alberta – Canada 

Experience Hours (Planning & Scheduling): 
7500
Experience Hours (Cost Management): 
4500
Experience Hours (Forensic Analysis): 
6000

Senior Planning Engineer, QDSBG Constructions, Lusail City Development Project

START Date: 
August, 2015

Project: Development of Infrastructure, Roads, Tunnel and LRT Station, Lusail City, Qatar

Client: Lusail Real Estate Development Company

Consultant: Parsons International / Dorsch Group

Main Contractor: QD-SBG Constructions

 

Duties and Responsibilities:

Experience Hours (Planning & Scheduling): 
2400
Experience Hours (Cost Management): 
2400
Experience Hours (Forensic Analysis): 
0

Senior Lead Planner, London Underground Limited, Tottenham Court Road Station

START Date: 
September, 2015
  • Responsible for all programming and planning activities on behalf of client.
Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
500

Project Manager, STT Enviro Corp, engineering, Procurement and Construction

START Date: 
January, 2016
END Date: 
September, 2016

Scheduling, Monitoring and Managing multidisciplinary complex projects.

·      Developed project documents such as scope statements, scope of work, schedules,  charters, reports and presentations, contract agreements, technical and commercial requirements, time and cost estimations, project coordination procedure and data flows, WBS and WF.

Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
450
Experience Hours (Forensic Analysis): 
450

Advisor - Planning and Scheduling, Hydro-Québec, Functional Group

START Date: 
June, 2016

- Validate the schedules prepared for Authorisation to Proceed milestone;

- Provide technical support to the Operational group;

- Participate in a pilot project for the implementation of EPM in an Operational division.
 

Contracts Senior Planning Engineer, BAE Systems, marine and offshore

START Date: 
July, 2014

Projects includes: ROYAL NAVY QUEEN ELIZABETH CLASS AIRCRAFT CARRIERS Location: Portsmouth, Govan, Tyneside, Merseyside & Rosyth Client: Aircraft Carrier Alliance Main Contractor: Imtech Contract Value: Circa £50 million Scope: Manufacture & Install HVAC & associated equipment Experience of all aspects of Planning Operations associated with the Construction of Process and Utility modules, semi-submersibles and FPSOs’ within the Offshore Oil and Gas industry for a period of sixteen years with system and application knowledge of Primavera P3 and P3e, Artemis 6000, 7000 and 9000 co

Experience Hours (Planning & Scheduling): 
2000

senior planner, BAE Systems, marine and offshore

START Date: 
July, 2014

Projects includes: ROYAL NAVY QUEEN ELIZABETH CLASS AIRCRAFT CARRIERS Location: Portsmouth, Govan, Tyneside, Merseyside & Rosyth Client: Aircraft Carrier Alliance Main Contractor: Imtech Contract Value: Circa £50 million Scope: Manufacture & Install HVAC & associated equipment Experience of all aspects of Planning Operations associated with the Construction of Process and Utility modules, semi-submersibles and FPSOs’ within the Offshore Oil and Gas industry for a period of sixteen years with system and application knowledge of Primavera P3 and P3e, Artemis 6000, 7000 and 9000 co

Experience Hours (Planning & Scheduling): 
2000

staff engineer, BASF, All Portfolio of Projects

START Date: 
February, 2016

Staff Planning Engineer: schedule development, control and risk/change management on medium/large projects (50-100 MM$)

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
100

AGM - Project Management, Yansab Petro chemical project, Major Turnaround 2016 BBTX,Polymer,HDPPE,EG,U&O.

START Date: 
February, 2015
Project start-up , communicationing , Coast Controlling, mobilization of new business, stakeholders relationship implement, safety standing committee advisory.
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1000