Project Control Lead - Sr Planner/Scheduler, worleyparsons Canada, Mix of Projects - Edmonton - FortMcmurray - Calgary

START Date: 
January, 2010
END Date: 
July, 2014

Project Control Lead

Sr Planning/ Scheduling Engineer

Worley Parsons – (Edmonton/ RedWater/FortMcmurray) – Alberta – Canada 

March 2013– July2014

 

NORTH WEST REDWATER PARTNERSHIP NWR    – (Edmonton/ REDWATER) – Alberta – Canada 

              Project :-  Phase 1 – Northwest Red Water Partnership ( NWR ) Bitumen Refinery in Sturgeon County .

                                 ( EPC Project )

                                It consists of the following six (6) primary processing units and their supporting tankage and utility

                                systems:

                               1. Unit 10 – Crude and Vacuum Unit

                               2. Unit 20 – Residue Hydro-cracking Unit

                               3. Unit 30 – Hydro-processing Unit

                               4. Unit 40 – Gasification Unit

                               5. Unit 50 – Light Ends Recovery Unit

                               6. Unit 60 – Sulphur Recovery Unit.

                        

                     Duties followed:-

•     Provide project control support to the projects in terms of planning, schedule and project reporting and progress & performance monitoring and systems. 

•     Enforce the compliance of project control systems, standards and procedures in particular planning and scheduling, and the best project control practices for consistency and uniformity.

•     Responsible to integrate the civil program, deep undergrounds and North Assembly Area schedules working with the Contractors scheduler’s, to provide the construction Managers, with the follow up weekly schedules.  

•     Much more involved in the overall Schedule Integration focusing on Module RAS dates and contractor mob dates.

•     Preparation of weekly, monthly progress and historical reports, Budget & Cost control reports as well as Monthly forecast reports

•     Responsible for development, integration and update of contractors’ schedules into integrated master schedule.

•     Advice management regarding forecasted costs overruns of approved budgets and recommends corrective actions.

 

·         General follow up for the  Company  going on projects  between Edmonton, Calgary and Fortmcmurray areas

(Oil & Gas Industry) Branch

1.      Enbridge

Demolishing and Removal 34 inch buried piping & Installation of new NPS 24inch (4.5 Km length)

2.      MEG Energy

Christina Lake Regional Project - Well PAD A,B, C, D, E&F  lnfill Expansion

3.      MEG Energy

Christina Lake Regional Project -Ph.2 Debottlenecking Project

Oil Remover Filter (ORF) WR -1051, Sales Oil Trim Cooler 2-E-197 WR -1052,

Emulsion Heaters WR -1053, PW / Glycol Exchanger WR -1054

4.      Pembina Infrastructure and Logistics LP :-

         REDWATER FRACTIONATION SITE II – EPC Project

Construction of a  grassroots fractionation plant north of the existing Redwater NGL Fractionation Plant, near Redwater, Alberta, and is intended to be a twin of the existing Redwater fractionation facility built in 1998 for Novagas Canada Ltd.

 

•     Provide staffing guidance to Engineering and Construction supervisors in the areas of planning and scheduling by analyzing and evaluating all relevant and pertinent data.

•      Development of the Project WBS and assist in building the whole over EPC Master Schedule in conjunction & Cooperation with Worley Parsons team work groups, starting from the early stages of any project up to the most detailed schedule levels used to follow all of the project related life cycle stages including all related contractors, subcontractors, Disciplines, through the agreed WBS of the Project.

•     Discuss, coordinate and resolve long term and short term planning and scheduling problems with personnel throughout the company and with contractor organizations.

•     Development of all detailed work schedules for the Engineering Work Packages (EWP) using Primavera Project Planner P6 software

•     Preparation of weekly, monthly progress and historical reports, Budget & Cost control reports as well as Monthly forecast reports

•     Providing schedule, progress, and claim analysis to Area Manager and Resident Engineers.

•     Guiding and supporting area project controls direct reports.

•     Responsible for development, integration and update of contractors’ schedules into integrated master schedule.

•     Collect, interpret and input schedule data into the project control database and provide output to the project team, assist in preparing status reports and other related project planning and control documentation.

•     Advice management regarding forecasted costs overruns of approved budgets and recommends corrective actions.

•     Define project needs for cost control in accordance with contractual requirements, objectives and Company procedures.

•     Providing schedule, progress, and claim analysis to Area Manager and Resident Engineers.

•     Guiding and supporting area project controls direct reports.

•     Responsible for development, integration and update of contractors’ schedules into integrated master schedule.

 

Principal Project Controller

Worley Parsons – BAHRAIN           TATWER PETROLEUM BAHRAIN Field Development Company

Kingdom of Bahrain – Manama

August 2011–Feb-2013

Project: - TATWER PETROLEUM BAHRAIN Field Development Company

(Supply of Facilities Engineering/ Procurement  and Construction Resources – EPC Project )

•     Efficient and effective production of industry standard engineering deliverables as well as providing support to the functions of procurement, construction, commissioning, close out and document control.

•     Design Engineering Support for the company development program, in compliance with Good International Petroleum Industry Practice (GIPIP).                                                                                

•        Applying WorleyParsons  Project Control procedures for all of my entitled projects as a project control lead, Planning & Scheduling  and Cost Control

•     Development of the whole over Engineering/Design/ Procurement/ Construction Master Project Schedule  in conjunction & Cooperation  with WorleyParsons team work groups, starting from the early stages of any project up to the most detailed schedule levels used to follow all of the project related life cycle stages including all related  contractors , subcontractors , Disciplines, through the agreed WBS of the Project.

•        Development of all detailed work schedules for the Engineering Work Packages (EWP) using Primavera Project Planner P6 software’s.

•        Follow up for progress of works of projects in conjunction with specifications and issued plans, aid in development and maintenance of manpower and quantity curves.

•        Preparation of weekly, monthly progress and historical reports, Budget & Cost control reports as well as Monthly forecast reports.

•    Collect, interpret and input schedule data into the project control database and provide output to the project team, assist in preparing status reports and other related project planning and control documentation.

 

Project Control Lead (Senior Planner/Scheduler)

Worley Parsons - Canada – Alberta

                                                                            SUNCOR ENERGY – FortMcmurray

                                                            Sustaining Projects:-Mining/ SWWM/ Infrastructures Projects – EPC Project                      

January2010 – August2011

•        Development of the whole over Master Projects Schedules  in conjunction & Cooperation  with SUNCOR  team work groups ( Engineering, Procurement and Construction  Teams ),  starting from the early stages of any project up to the most detailed schedule levels used to follow all of the project related life cycle stages including all related  contractors , subcontractors , Disciplines, through the agreed WBS of the Project.

•      Supervisingscheduleandprogressreportingdevelopment,maintenance,monitoring,andanalysis forSUNCOR Sustaining Projects Department.

•       Applying SUNCOR Project Control procedures for all of my entitled projects as a project control lead, Planning & Scheduling and Cost Control

·         Develop Projects WBSs using the latest project planning and scheduling tools, eg Primavera.

·         Plan and provide work direction as required in the preparation of planning and scheduling control systems and practices to provide Engineering, Procurement and Construction supervisors the means to evaluate the progress and execution of assigned projects.

·         Provide staffing guidance to Engineering and Construction supervisors in the areas of planning and scheduling by analyzing and evaluating all relevant and pertinent data.

·         Analyze major capital projects to plan the effective execution sequence based on current industry practices.

·         Discuss, coordinate and resolve long term and short term planning and scheduling problems with personnel throughout the company and with contractor’s organizations.

·         Assist Project Engineers in contractual cost compliance during negotiations of scope changes.

·         Development of all detailed work schedules for the Engineering Work Packages (EWP) using Primavera Project Planner P6 software’s.

·         Follow up for progress of works of projects in conjunction with specifications and issued plans, aid in development and maintenance of manpower and quantity curves.

·         Preparation of weekly, monthly progress and historical reports, Budget & Cost control reports as well as Monthly forecast reports.

·         Collect, interpret and input schedule data into the project control database and provide output to the project team, assist in preparing status reports and other related project planning and control documentation. 

Experience Hours (Planning & Scheduling): 
7500
Experience Hours (Cost Management): 
4500
Experience Hours (Forensic Analysis): 
6000