Programming Engineer I, MTR Corporation Ltd (MTRC), Express Rail Link

START Date: 
June, 2010

Programming, Master Programme and detail programme review, progress monitoring, S-curve, earned value, KPI, Labour resources.

Supervision of contractors, review of programme, progress monitoring and reporting.

Claims analysis and accreditation.

Experience Hours (Planning & Scheduling): 
6400
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
800

Planner / Scheduler, Carillion Canada, Civil Works

START Date: 
April, 2014
END Date: 
April, 2017

Kindly bear with me as this will be populated soon .

Experience Hours (Planning & Scheduling): 
6600
Experience Hours (Cost Management): 
6000
Experience Hours (Forensic Analysis): 
6000

Senior Planner, Siemens S.A.E., Nile Ritz Carlton Hotel

START Date: 
April, 2008

Current Job:

Jobtitle:Senior Planning Engineer

Employer:Siemens Technologies S.A.E.

From:April 2008

Job description:

  • Preparing & updating time schedules for MEP works using Primavera Project Planner 3 & 6 and Microsoft project.
  • Preparing monthly reports.
  • Preparing claims for time extensions.
  • Preparing Progress payments for MEP works.
  • Preparing variation orders.

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
12000

Planning Engineer;Senior planning engineer; deputy planning manager, CSCEC Middle East, R902/1 - Improvement of Emirates Road-stage2;Outer By Pass Extension;Internal Roads and infrastructure for Military

START Date: 
August, 2008

COMPNAY 1:  China State Construction Engineering Corporation (Middle East) (L.L.C)

OVERALL RESPONSABILITY: 

      Study of project documents and also based on requirements from the Client, preparation and submission of Baseline program of works with the consult of Project Manager’s advises for the sequence of works. Monitor & Control of the works with periodic review and updated of the project planning based on requirements.

   Project 1:

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
8000

SENIOR PLANNER, NJS Consultants, Al Amerat Waste Water Project

START Date: 
September, 2003

 

SIVASANKARI

 

Email ID:  sivasankarisundar@gmail.com      Mobile: +968 -92615196

 

 

SUMMARY

Experience Hours (Planning & Scheduling): 
15000

Planner, NJS Consultants, Al Amerat Waste Water Project

START Date: 
September, 2003

 

SIVASANKARI

 

Email ID:  sivasankarisundar@gmail.com      Mobile: +968 -92615196

 

 

SUMMARY

Experience Hours (Planning & Scheduling): 
15000

SENIOR PLANNER, NJS Consultants, Al Amerat Waste Water Project

START Date: 
September, 2003

 

SIVASANKARI

 

Email ID:  sivasankarisundar@gmail.com      Mobile: +968 -92615196

 

 

SUMMARY

Experience Hours (Planning & Scheduling): 
15000

Construction Claims Consultant. Projects Planner and Scheduler. , CEHACO, 1) Infrastructure 2) Sewerage Treatment Plant 3) Bridge works 4)Building works

START Date: 
April, 2014

Build Construction Claims, Scheduelling, Outsourcing Engineers and many other duties. Focusing now on being Professional with Primavera. 

Project Control Manager/ Forensic Planner, STRABAG, Pabianice Express Road Bypass S14

START Date: 
December, 2008
END Date: 
April, 2012

Setting the Contractor strategy ant the contracting politics.

Claims and Variation manageing

Planning and Scheduling in MS Project & Asta Power Project.

Setting the main assumptions for critical path and technological procedures for Time Schedule, ongoing verifiation and adaptation.

Contractor representation in front of Employer and Engineer.

Controling the on-site activity in accordance to signed Contract, Building Law, Public Procurement Law and Common Law.

FIDIC General Condidtion guiding and approach to all on site activity

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Forensic Analysis): 
4000

Senior Planning Engineer, PT. Punj Lloyd Limited, All EPC and I project both offshore and onshore.

START Date: 
June, 2006
END Date: 
June, 2013

1.       Responsible for updating the level 2, 3, 4 schedules including Project Baseline,engineering, Procurement, Construction and Installation.

2.       Updating the Master document register, Procurement Control Sheet, Manning Histogram and controlling the activities.

3.       Preparation of S-Curve for E, P, C, I and monthly updating.

Experience Hours (Planning & Scheduling): 
14000
Experience Hours (Cost Management): 
12000