Senior Planning Engineer

Senior Planning Engineer, Chiyoda Almana Engineering LLC, Gas To Liquid

START Date: 
September, 2014

Planning & Scheduling on an EPCm company for Qatar Shell Gas To Liquid projects

Senior Planning Engineer, Engineering Kinetics Limited, 225MW Diesel Power Plant

START Date: 
July, 2008
END Date: 
April, 2009

Project : OMV Sawan Compression Station for ABB Italy.

The scope of Project was Fabrication of Steel Structure (500 Tons) for Sawan Compression Station.

Project Budget was 118 Million Rs. My role as Project Engineer includes the following responsibilities.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500

Senior Planning Engineer, FAUZ Engineering Limited, Engro Fertilizer Plant

START Date: 
April, 2009
END Date: 
November, 2012

I have lead Project Planning and Contracts department in FAUZ Engineering, and responsible for overseeing running site projects, with respect to progress, invoicing, and payment follow-ups.

Worked on the planning and initialization of the following projects

 

  • ENGRO Foods Supply Chain Limited

Scope of Work Includes Fabrication and Erection of Storage Tanks

Experience Hours (Planning & Scheduling): 
3100
Experience Hours (Cost Management): 
700

Senior Planning Engineer, Lagan Construction JV, New Islamabad International Airport

START Date: 
November, 2012

I am working as senior planning engineer on “New Islamabad International Airport”. Main job responsibility is as follows:

Ø  Produced work schedules for Main/Emergency/Secondary Runways, Aprons, Service Roads, Perimeter Track, Underpasses, Bridges, Drainage System, Water Works, Water Supply & Fire Water Piping System (67Km UG Pipeline), Steel Bridges, Sewerage Treatment Plant & Lift Stations

Ø  Gathered/ Analyzed & distributed work performance reports

Experience Hours (Planning & Scheduling): 
2800
Experience Hours (Cost Management): 
1550

Senior Planning Engineer, RLB | Rider Levett Bucknall, Various Projects (Safety Improvements / Product Diversification / Obsolesence)

START Date: 
April, 2013

Responsible for producing credible, fully resourced and costed project schedules for various projects (modification - production / safety related, replacement of obsolete equipment, new processes).

Maintaining schedules current, and reporting deviations.

Producing KPIs.

Experience Hours (Planning & Scheduling): 
1400

Senior Planning Engineer, Simon Carves Ltd., New Build Polyethylene Plant for China

START Date: 
April, 2012
END Date: 
March, 2013

Responsible for:

Producing a credible, fully resourced and costed project schedule.

Maintaining schedule progress.

Highlighting areas of concern re; progress.

Producing KPIs.

Experience Hours (Planning & Scheduling): 
2000

Senior Planning Engineer, Kuwait, Commercial Mall

START Date: 
January, 2013

 Writing of technical and detailed reports, especially in Construction Management, Planning, Scheduling, Cost Analysis, and Monthly Reports, Cash flow, Method of statment, and Update Schedules.

Senior Planning Engineer, Mott MacDonald Limited, GazProm's Badra Field Development at Iraq

START Date: 
May, 2013

Senior Planning Engineer / Project Interface Coordinator with Mott MacDonald Limited in Dubai, UAE

Senior Planning Engineer, PT. Punj Lloyd Limited, All EPC and I project both offshore and onshore.

START Date: 
June, 2006
END Date: 
June, 2013

1.       Responsible for updating the level 2, 3, 4 schedules including Project Baseline,engineering, Procurement, Construction and Installation.

2.       Updating the Master document register, Procurement Control Sheet, Manning Histogram and controlling the activities.

3.       Preparation of S-Curve for E, P, C, I and monthly updating.

Experience Hours (Planning & Scheduling): 
14000
Experience Hours (Cost Management): 
12000

Senior Planning Engineer, Stoneworks Co. Inc., Ayala Life FGU Bldg., ICEC Office Bldg., Pacific Plaza Tower Condominium

START Date: 
January, 1998
END Date: 
January, 2000

The Stoneworks Co. Inc.

Location:Philippines

Project: Ayala Life FGU Office tower, ICEC office tower, Pacific Plaza Tower condominium

Date Join: (January 1998 – February 2000)

Senior Planning Engineer

§  Working as part of the Construction Department

§  Duties include planning, managing and controlling cost resources.

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
4000