Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Planning & Scheduling

PLANNING ENGINEER, CSCEC Middle East, Civil Infrastructure

START Date: 
May, 2009

I am working as a Planning Engineer in Dubai UAE

Brief description of my role;

-Define activitities, duration, relationships & resources and prepare schedule for tender programs

-Prepare planning reports for tender submittals

-Prepare detailed programs & reports for assigned projects

-Assist with Project Management

-Preparation and documentation of reports of interest to Project stakeholders showing the status & health of the project

-Forecasting the project parameters

PLANNING ENGINEER, Bahrain, RAMSIS ENGINEERING, Oil & Gas Field Maintenance Services

START Date: 
March, 2012

 

Activities & Responsibilities:

§  Project Progress Monitoring

§  Scheduling

§  Planning & Intra discipline Co-Ordination

§  Material Management

§  Quantity take-off

§  Performing Delay Analysis

§  Development of Progress Measurement System

Planning & Scheduling Professional, Boeing Australia, ADF F-111 Weapon System Business Unit Amberley, Australia

START Date: 
October, 2001
END Date: 
January, 2004

ADF F-111 Weapon System Business Unit Amberley, Australia (Oct 2001 – Jan 2004) Planning & Scheduling Professional

  • Responsible for the operation, maintenance and oversight of the project master schedules for the deeper level maintenance of F-111 aircraft
  • Primary responsibility for overall schedule integrity; schedule establishment; baseline maintenance; critical path analysis; and identification of potential issues and impacts
  • Mentoring and tutoring of junior team members; identifying areas for process

Work Package Co-ordinator, Aker Solutions, Albacora, Morvin

START Date: 
February, 2007
END Date: 
September, 2009

Work Package Co-ordinator employed to manage Aker Solutions Subsea Data, Systems and Software projects, the products developed in the department are the iConSCU and PLC based topside control systems. Each project involves coordinating hardware engineers, software engineers and a test team as well as interfacing with the overall project manager, technical authority, clients, project planners and department managers in addition to overall administration and control of the project.  The purpose being to deliver a project on budget and on time. 

1.“planning engineer” or “project planner” or Forensic Analysis, Chubb Systems Ltd, Construction of defence and Installation

START Date: 
December, 2011
END Date: 
June, 2012

 

·           Taking part in project familiarization & understanding process through project documentation review and project walkthrough.

·           Conduct delay Investigations as-built schedule programmes

Sr. Planning Engineer, Habib Rafiq (Pvt) Ltd., Construction of Women’s Hostel at FC College Lahore.

START Date: 
June, 2012

 

Working at Habib Rafiq (Pvt) Ltd as Sr. Planning Engineer,   

 

Planning/scheduling and monitoring the projects using MS Project/Primavera. Dealing with Cash flow estimates, methodologies, manpower deployment and physical progress plans/histograms. Preparation of procurement plan for material etc      

Assistant Scheduler, Doosan Heavy Industies and Construction Co. Ltd, De-Salination

START Date: 
May, 2011

qPreparation & Tracking of the project master schedule and Man power histogram.

qIdentification & Monitoring of critical paths running through the project master.

qWeekly/Monthly/Daily reports generation including ‘S’-curves for client & management review.

qJob allocations to all discipline Engineers and follow up for daily job progress.

1.“planning engineer” or “project planner” , ENKA Construction & Industry Co. Inc., SIPD Early Production Facilities ME&I Works-Basra IRAQ

START Date: 
June, 2006
END Date: 
May, 2012

Scheduling  Planning Engineer at ENKA

 

Progress Reporting

Daily, Weekly and Monthly Reports

Estimating and Look ahead Plans

Client Communication and bla bla

PLANNING ENGINEER / CIVIL ENGINEER, Arvind Techno Engrs Ltd, Construction of Four Lanning of NH-25 from Km 59.500 to Km 75.500 of Lucknow – Kanpur section.

START Date: 
October, 1998
END Date: 
November, 2001

 

  • Responsible for Overall construction, execution and supervision of ‘4’ Minor bridges (Span varies form 12.0m to 31.0mt), Culverts etc. as per the standards and specifications laid down by MORTH.
  • Working out Actual Quantities as per the Cross sectional details given in the drawings.
  • Preparation of Weekly / Monthly Progress Reports.

              Preparation of Petty Contractors bills

Market Place