Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Lead Planner

Lead Planner, Tubelines, Piccadilly line upgrade

START Date: 
January, 2008
END Date: 
November, 2010

Tube Lines has a 30 years Public Private Partnership (PPP) contract with London Underground for the maintenance and upgrade of the entire infrastructure on the Jubilee line, Northern line and Piccadilly line.

Project Handled

 

  • UKP 2.1 billion Piccadilly line upgrade including rolling stock, signalling and enabling works.

 

Lead Planner, Petro Part, South Pars Gas Field Development - Phases 15&16 - Onshore Refinery Facilities

START Date: 
January, 2009
END Date: 
March, 2010

Project involved:
South Pars Gas Field Development - Phases 15&16 - Onshore refinery facilities , January 2009 - March 2010 

Lead Planner, Rotary Engineering Limited, Singapore Parallel Train project

START Date: 
November, 2009
END Date: 
November, 2010

Adopt in preparing Master schedule incorporated with Manpower & Equipment requirement.

Co-ordination with Clients regarding the schedule, progress requirements, achievements & other requirement.

Co-ordination with all discipline Planners, Superintendents and Managers regarding the schedule & progress.

Co-ordination with other contractors in respect of the work fronts availability, schedules & requirement.

Preparation of Weekly reports & Monthly reports for Internal & External Management.

Preparation of Two weeks & Three Months L

Lead Planner, Grinaker LTA, Polifin PVC Expansion Project

START Date: 
January, 1993
END Date: 
December, 1995

Group projects planner. Co-ordination, checking & detailing of all programs for various project sites, that include a hands on approach. Liase with client, suppliers & fabricators. Going to various sites and fulfilling planning functions, to reschedule and re evaluate environment with changes in scope and contract.
1996 Namdeb Floating Treatment Plant. Level 4 programs for fabrication of barge, structural steelwork, platework and piping.
1996 Goldfields Refrigeration Pipeline. Installation of pipeline for Mine chilled water system.

Experience Hours (Planning & Scheduling): 
5850
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
150

Lead Planner, AMEC Power & Process Europe, Hole House Underground Gas Storage Phase 3

START Date: 
September, 2011
END Date: 
August, 2012

Lead planner on underground gas storage EPC project for key client EDF Energy.

Responsibilities include maintenance of Project Programme in Primavera P6, Supervision of the Progress Measurement database and Earned Value reporting.

Lead Planner, GATE Terminal B.V., GATE LNG TERMINAL PROJECT

START Date: 
May, 2008
END Date: 
July, 2011

Co-Lead Planner in an important LNG Project based in The Netherlands

Lead Planner, Ghelamco, Marynarska Business Park

START Date: 
March, 2007
END Date: 
January, 2008

Lead Planner

*Marynarska Business Park

Main duties:managing investment documentation,production of detailed target / baseline construction programme, monitoring and updating progress, regular report to construction director, critical path analysis using Primavera P6 software. Planning advise and support to project team were required re-scheduling.

Lead Planner, Network Rail, All Great Western Region Projects

START Date: 
November, 2003
END Date: 
May, 2004

November 2003 to May 2004
Network Rail – Lead Planner/Programme Controls Manager     
Rail
Lead Planner for Investments delivery division covering Signaling, Telecommunications, Electrification and Plant Projects. Responsibilities include the supervision of all planning staff, ensuring that processes are followed and monitoring data/schedule integrity and producing reports for senior management.

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
50

Lead Planner, SEG Qatar WLL, EPIC for Raslafan Emergency Safety College

START Date: 
June, 2002

I am Project Management Professional , Planning & Scheduling Professional & a Civil Engineer working in Qatar with SEG Qatar WLL on a unique EPIC project of the MENA region for the past 21 Months.

Lead Planner, Shapoorji Pallonji & Co Limited, Building & Infra Works

START Date: 
June, 2002

Current Role Lead Planner

  Key Responsibility :

 

  • Prepare and update Project Schedule based on the contract.
  • Set work program and target milestones for each phase based on the project plan.
  • Forecast Manpower requirements, Material Procurement, Formworks movements and Monthly Cash flow.
  • Monitor critical activities based on the project schedule and advise project management.(Weekly R