Lead Planner, Shapoorji Pallonji & Co Limited, Building & Infra Works

START Date: 
June, 2002

Current Role Lead Planner

  Key Responsibility :

 

  • Prepare and update Project Schedule based on the contract.
  • Set work program and target milestones for each phase based on the project plan.
  • Forecast Manpower requirements, Material Procurement, Formworks movements and Monthly Cash flow.
  • Monitor critical activities based on the project schedule and advise project management.(Weekly Risk Analysis, Area of Concerns)
  • Monitor Engineering submittals and Engineering activities(Shop Drawing & Material Submittals, Material verification & approval, NCRs, Procurement follow ups, Flow charts preparation)
  • Prepares and submit updated work program and cash flow curve showing actual progress and identify areas of weakness and establishes means and methods for recovery, if any, as well as new critical activities.

 

 
  • Monitor day to day work progress and prepare the weekly and monthly program and report. Conduct weekly Progress meetings.
  • Maintain and record update of site work progress obtained from PM
  • Report to the Project Manager about the current work progress and make comparison between plan and actual progress, study impact of alternative approaches to work.
  • Participate in project meetings and discussions with the Client.
  • Prepare Time Extension analysis.
  • Assists in preparing work program, cash flow and manpower histogram for tenders.
  • Performs other duties and responsibilities as assigned .

 

  • AREA OF KNOLODGE & WORK EXPERIENCE

    • Excellent Knowledge & Experience for implementation of planning in site works,.
    • Very Good Knowledge & Experience in Analytical methods, Construction Methodology, QA/QC Procedure, HSE implementation, MEP works
    • Knowledge & Experience in Quantity Survey (Preparing Cost Estimates, Measurement Sheets, Allocation of manpower and Productivity, Comparison Sheet & Payment for Supplier and Sub Contractor, Financial Control Systems, Variation, Contractual Claims and Final accounts, Monthly Progress Payments).
    • Have a very Good Knowledge & Experience in QA/QC works (Implement & Manage QA/QC Programmes as per Company QCP, Preparing Method Statements, Document Control System, MAR Submittals, Testing, NCRs, Quality Audits & Meetings, , As Built documentation, O & M Manuals.
    • Have an Excellent Skill set in Site Management/Works. Well experienced in Site Execution works, Waste Control, Labour Management, Construction Methodology. Execution of works as per Shop Drawing, Specification & Cost Control.  Well experienced in HSE implementation.
    • Experience in Infrastructure works.
  • PROJECTS DETAILS    - QATAR - Aug 2010 to Till Date - 1 Year – SHAPOORJI PALLONJI QATAR, W.L.L

    A.

    •  Period                          : Aug 2010 to till date
    •  Position                        : PLANNING ENGINEER
    •  Project                         : Design & Construction of Barwa City Phase 1 Amenities
    •  Client                           : BARWA
    •  Project Value             : 676 Million QR

    B.

    PROJECTS DETAILS    - UAE - Aug 2006 to Till Date - 4 Years – CODE Contracting Company (L.L.C) 

    A.

    •  Period                          : Nov 2008 to till date
    •  Position                        : PLANNING ENGINEER
    •  Project                         : Construction of New Schools Complex, Construction of 33/11KV Substation
    •  Client                           : ADNOC (Abu Dhabi National Oil Company)
    •  Project Value             : 315 Million AED

    B.

    •  Period                          : June 2007 to Nov 2008  
    •  Position                        : PLANNING ENGINEER, QA/QC ENGINEER,
    •  Project                         : TWIN TOWER BUILDING (18 Floors + Swimming Pool at Top Roof)
    •  Project Value             : 160 Million AED

    C.

    •  Period                          : August 2006 to June 2007  
    •  Position                        : PLANNING ENGINEER, Quantity Surveyor,
    •  Project                         : WATER SUPPLY GHAYATHI AND AL HAMRA (100KM Pipeline + Pump Room)
    •  Client                           : ADWEA (Abu Dhabi Water and Electricity Authority)
    •  Project Value             : 85 Million AED

     D.

    DETAILS - INDIA - June 2002 to Aug 2006 - 4 Years – CHANDRASEKAR ENGINEERS & CONTRCTORS

    • Construction of Zonal Office in MIT – Projects Engineer - Chrompet – Chennai – DOT – 100 Mil INR
    • Construction of School Building in Pallavaram – Projects Engineer - Chennai – PWD – 90 Mil INR
    • Construction of school Building in Kovilambakkam – Projects Engineer - Chennai – PWD – 9 Mil INR
    • Construction of Medical College in Chengleput – Sr Site Engineer - PWD – 150 Mil INR
    • Construction School Building in Chengleput,- Sr. Site Engineer -  PWD – 8.6 Mil INR