etc.

Lead Planner/ Planning Manager, Costain Ltd, Water, Wastewater, tunnels, defence, etc.

START Date: 
August, 2020
END Date: 
April, 2022

Recruited to lead on a major water pipeline project. Had 3 supporting planners, but unfortunately the "Production Managers" thought they were in control of the project and how it should be planned. Highlighted various issues on the project as there was a belief because it was linear that it could be handled like a production line, but there was no consideration for the 400km's of GI, SI, 1400 crossings, ecology, archaeology, land owners, restricted access, construction limited times due to transport and areas such as schools, significant logistics, etc.

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
400

vice president of association, SKEMA Business School, Mid-autumn Festival, China Day, etc.

START Date: 
September, 2016

Vice president of New Silk Road Student Association: Heading art department, collaborating on strategy, managing personnel, reporting to the president

Consultant and Project Controls Manager, AMEC, etc., New Main Oil Line, UZ715 EPC1

START Date: 
April, 2011
END Date: 
December, 2014
Project Controls Coordinator providing PMC supervision over a portfolio of multi-billion dollars (any project with a value bigger than 50 million dollars or strategic project) and Project Controls Team Lead for EP projects. Project Controls Coordinator ensuring the PMC contract is managed and delivered to AMEC and ZADCO technical satisfaction; responsible to provide leadership in the development/update and implementation of processes, procedures, methodologies, to ensure the project management group is resourced with the correct disciplines and size to deliver the IPMT to the requirements of
Experience Hours (Planning & Scheduling): 
3950
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
500

Senior Engineer (Planning) , FEDO (FACT Engineering and Design Organisation), India, detailed engineering and construction of Fertiliser, Chemical, Oil tank farms, cross country pipe lines, etc.

START Date: 
April, 1997
END Date: 
March, 2003

Responsiblities:

·        Planning of projects including Preparation of Starter Schedules, Detailed Project Schedules using Primavera Project Planner (P3) & MS Project, Preparation of suitable Work Breakdown Structures, Progress Measurement System, S curves, Prioritization of Activities, Forecasting of activities, Progress monitoring and reporting.

Area Planning Manager, BK ASIA PACIFIC LIMITED, Railway Projects, High Rise Buildings, Water Supply System, Power Stations, etc.

START Date: 
February, 1998

Over 23 years experience, including 14 years in Hong Kong and PRC, in the preparation, updating and maintenance of contract and project programmes, and progress monitoring of various civil engineering and building projects.

Tender planning, contract planning, detailed planning, and programme delay analysis for construction claims and disputes involving Mass Transit Railway Corporation, Airport Authority, Housing Authority and other government and private development projects in Hong Kong.