Airports / Aviation

Program Scheduler, Sierra Nevada Corporation, aerospace shuttle development

START Date: 
March, 2014
END Date: 
September, 2014

Member of a team of 6 schedulers each assigned multiple parts of aerospace shuttle project working with engineers to build details into multi-year master schedule.   

Experience Hours (Planning & Scheduling): 
900
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

Junior Planning Engineer, Faithful + Gould, Heathrow Airport Limited, Q6 Asset Management Programme

START Date: 
May, 2016

Preparing, monitoring and updating an integrated programme containing 200+ projects, successfully tracking milestones/gateways up to the Final Investment Decision. Ensure communications and collaboration between on-site Contractors and Design Contractor as well as buidling similar relationships with the Client, reviewing progress on a weekly basis and issuing client reports displaying progress status.

 

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

Planning Manager, Mace, Pier 6 Vertical Segregation

START Date: 
August, 2003
END Date: 
July, 2005

Planning Manager - Asta Power Project, MSP

Aviation, Baggage Systems, Water Projects, Aviation Building and Infrastructure

Experience Hours (Planning & Scheduling): 
4000

Engineer, Al Habtoor Engineering Enterprises, Dubai International Airport Expansion Phase 2

START Date: 
February, 2005
END Date: 
February, 2007

I was part of the amazing team building the Dubai International Airport expansion Phase II (Contract AX059). It was a great experience and I have learned a lot from this job.

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
0

Air Traffic Control Assistant, Oxford Aviation Services Ltd., Civil Aviation

START Date: 
December, 2012
END Date: 
May, 2016

Air Traffic Control Assistant. Assisting Air Traffic Controllers in their duties to maintain the safe, swift and efficient flow of aircraft traffic on the ground and in the air, with the team at London Oxford Airport.

 

My duties included Programming the Slot System at the airport, producing Flight Strip information from processing Flight Plans and VFR Flight Notifications, Producing Weather Reports and communicating with Pilots, other Units and emergency services, as well as dealing with the public on occasion.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

Planning Engineer, Murray and Roberts Contractors (Middle East) LLC, International Airport

START Date: 
May, 2007
END Date: 
June, 2008

Murray and Roberts Contractors (Middle East) LLC

Ground Floor, Dubai National Insurance Building, Sheikh Zayed Road,

P.O. Box 30023, Dubai, United Arab Emirates

www.murrob.com

 

Duties and Responsibilities:   

 

Project Planning Engineer

 

Experience Hours (Planning & Scheduling): 
3950

Senior Planner, Daifuku Logan, GAL Pier 6

START Date: 
May, 2014
END Date: 
December, 2015

Senior Planner on Airport baggage projects.

Bids and live projects.

Primavera P6.

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Forensic Analysis): 
500

Mark Sales

First Name: 
Mark
Last Name: 
Sales

A planner with seventeen years experience in airports, infrastructures and defence.

Professional Since: 
Nov-2000 (25.0 yrs experience)
Oldest experience: 
Nov 2000 (25.0 yrs experience)
Years Experience: 
15
Guild Accreditation: 
GPC Member
GPC Member Since: 
Mon, 2016-06-06 (All day) - Wed, 2055-05-05 (All day)

Construction Project Planner / Senior Planner / Forensic Analyst, Kier, GAL MSCP6

START Date: 
January, 2016

Senior Planner - Pre-Construction / Senior Planner - Construction

Planning for bids and live construction projects.

Primavera P6

ASTA Powerproject

MS Project

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
100

Site Planning Engineer, Atkins Faithful & Gould, New King Abdulaziz International Airport Development Project

START Date: 
August, 2011
END Date: 
May, 2015

·        Preparation of a comprehensive cost and resource loaded contract baseline time schedule for the Aprons, Taxiways, Load Centers, Airside Storm water network (Pipe and box culverts), Blue Water Network, Airfield Ground Lighting network and the associated Vault Rooms, Glycol Network, 400Hz Network, Fuel Hydrant Network from the Fuel Farm, Fuel supply network from Aramco depot, GSE Tunnel/Ramps and security checkpoints, by reading the design drawings (70%).