Lead Planning Engineer

Lead Planning Engineer, Black & Veatch, Europe Larger Combine Heat and Power Project

START Date: 
March, 2006
END Date: 
October, 2008

Conoco Phllips Oil & Gas Immingham ICHP2  EPC Project of 412 Mega Watt 

u  Managing EPC Program of 8,529 activities of construction, engineering and procurement in Primavera. Project contains 17 sub-projects and 9 sub-contractor.

u  Integration of sub-contractor projects into main project.

Experience Hours (Planning & Scheduling): 
5500
Experience Hours (Cost Management): 
5000
Experience Hours (Forensic Analysis): 
5500

Lead Planning Engineer, BP, Devenick & Andrew Area Development

START Date: 
July, 2010
END Date: 
December, 2011

Responsible for the planning internally and externally on two major projects (BP Andrew and Devenick) with a combined value of over £1bn.

Lead Planning Engineer, BP, Rehabilitation Project

START Date: 
March, 2005
END Date: 
September, 2007

Responsible for the planning team and for the integrated project schedule for Brownfield projects.

Lead Planning Engineer, Exterran, Shell Iraq Majnoon Oil & Gas Separation plant

START Date: 
March, 2011
END Date: 
December, 2011

Lead Planning Engineer (Eastern Hemisphere)

Managing a team of 8 planning engineers in head office and project sites.

LEAD PLANNING ENGINEER , ABENGOA (BEFESA AGUA), Madrid (Spain), EPC project of desalinization plant of Ténès (Algeria), EPC project of desalinization plant of Honaine (Algeria)

START Date: 
December, 2008
END Date: 
January, 2010

EPC project of desalinization plant of Ténès (Algeria) with a budget of 240 Million USD with a design specification for desalinization water rate of 200.000 m3 of potable water per day for 2 million people in the Nord of Algeria.

EPC project of desalinization plant of Honaine (Algeria) for the JV company between Abengoa and Sacyr with a budget of 180 Million USD with a design specification for desalinization water rate of 180.000 m3 of potable water per day for 1.5 million people in the Nord of Algeria.  

Lead Planning Engineer, Centrica Energy, Round 3 Windfarm Development - Rhiannon

START Date: 
July, 2013
END Date: 
October, 2014

 Lead planning engineer for Centrica Renewables division looking after the portfolio of live projects across the renewables business.

Lead Planning Engineer, Cimac Electrical and Automation W.L.L.,, automotive industry

START Date: 
May, 2012

·         Preparation of Project Schedule as per the Scope, Schdule maintain and update, and variance explanations.

·         Preparation of Detailed plans & Level-4 Schedule (As per Work breakdown Structure)

·         Preparation of Daily, 3 week Look ahead, Monthly Plan & progress Reports.

Lead Planning Engineer , Laing O 'Rourke, water Treatment Plant

START Date: 
June, 2002

q  Managing a team of 3 planners

q  Develop a Level 4 Integrated Schedule for Construction Scope of works.  

q  Integrated Engineering, Procurement, Construction & Commissioning Disciplines,

q  Tracking Progress, Weekly Schedule Update, Monitor impact on Critical Path

q  Analyzed the estimates for allocated Budgets to different Work-Packages for the project.

Lead Planning Engineer , Laing O 'Rourke, water Treatment Plant

START Date: 
June, 2002

q  Managing a team of 3 planners

q  Develop a Level 4 Integrated Schedule for Construction Scope of works.  

q  Integrated Engineering, Procurement, Construction & Commissioning Disciplines,

q  Tracking Progress, Weekly Schedule Update, Monitor impact on Critical Path

q  Analyzed the estimates for allocated Budgets to different Work-Packages for the project.

Lead Planning Engineer, China Petroleum Engineering & Construction Corp -CPECC, EPC Projects for Oil & Gas

START Date: 
July, 2007

Role and Responsibilities:

·         Ensure the development of the project schedule according to the commercial needs.

·         Ensure the implementation of the Planning and Progress Control System required by the contract complexity, riskiness and duration, in compliance with the Project Breakdown Structure, Company Standards and Contract specifications.

Experience Hours (Planning & Scheduling): 
17600
Experience Hours (Cost Management): 
15200