Planning Engineer, Al Jaber Group, Infrastructure works- Emirati Housing Community Phase-1, Infrastructure works-Al Ain Industrial City, Shuttle Bus Link Road- Yas Island, Yas Island Infrastructure Development

START Date: 
May, 2008
END Date: 
January, 2012

 

·         Managing Early Warnings and claims with respect to time and cost.

·         Setting up Sustained management of dedicated control of progress profiles updated CAD files, Contractors look ahead programmes.

·         Develop Master programme in Primavera P5 and P6 using EPS and WBS structure to meet project control criteria.

Experience Hours (Planning & Scheduling): 
6900

Lead Project Planner, OIEC, 20 and 21 Phases of South Pars Gas Field Development

START Date: 
July, 2011

 

Dates

July 2011 Onwards

Occupation held

 Project Planner

Main activities and responsibilities

Junior Planner / Scheduler, Bombardier Transport Systems, King Abdullah Financial District Monorail

START Date: 
March, 2011

Junior planner & scheduler responsible for assisting senior schedulers and project core team with progress tracking and reporting for the King Abdullah Financial District Monorail Project.

PLANNING MANAGER, China State Construction Engineering Corporation (CSCEC), CITY OF DREAMS - Hotels & Casino Resort

START Date: 
May, 2006
END Date: 
September, 2010

PLANNING MANAGER for:

"City of Dreams - Hotels and Casino Resort" - Macau (approx. USD 3B)
CASINO RESORT featuring 2000 hotel rooms and an underwater themed gambling casino.
A joint venture project (Leighton-China State-John Holland JV) for the design & build of:

4 nos. of luxury HOTELS

  • 34 flrs - Crown Hotel
  • 30 flrs - Hardrock Hotel
  • 32 flr-Hyatt Regency
  • 35 flrs-Grand Hyatt

Casino & Retails:

  • 34,500 sq.m. Retails and Casino Gaming Area


 

Senior Planning Consultant, IPECC Consultants, Tuwairqi Steel Mills - Providing Project Planning & Scheduling Services

START Date: 
June, 2007
END Date: 
September, 2011

PROJECTS' EXPERIENCE

  1. Tuwairqi Steel Mills - Providing Project Planning & Scheduling Services

  • June 2007 to August 2007
In DRI project, Tuwairqi Steel Mills Limited (TSML) was looking for a firm to provide Project Management Consultants (Programs Manager, Project Managers, & Project Control Officers) to work closely with the client in order to manage & deliver the project with it Project Management methodologies, too

Project Controls Manager, Dragados Offshore SA, Eldfisk II 2/7s jackets

START Date: 
October, 2011
END Date: 
October, 2012

Project Controls Manager on oil & gas jackets construction for north sea client.

Site Planning Engineer, National Grid - Electricity East Alliance , National Grid - Refurbishment Norton Spennymoor 400kv and New Line Tees Crossing

START Date: 
January, 2011

·         Develop, optimise, and agree assigned project  programmes covering the construction aspect of the programme , including milestone definition/achievement, resource planning, cost control  and outage planning, to deliver the work with Asset Management, Network Operations, the Construction Programme Manager, Delivery Manager, Development Manager and Design Manager.

 

Scheduler, JACEC, Construction of Facility Building and Roads

START Date: 
September, 2010

* Management of  Integrated Master Schedules.

* Development and reporting of Earned Value Management (EVM) outputs in consultation with Programme Finance.

* Analysis & Coordination of Programme Finance data.

* Coordination of programme risks & opportunities via the Active Risk Management (ARM) risk management tool.

* Preparation of the routine project management reports and review packs.

* Development and reporting of programme metrics.

Contract and Project Controls, Kenny Construction, Gardnerpark - Central Wisconsin & Morgan-Werner West Transmission & Distribution project

START Date: 
November, 2007
END Date: 
February, 2010

Northeastern Wisconsin and the Upper Peninsula of Michigan are served electrically by 345- and 138-kilovolt transmission lines that are some of the most constrained in the ATC system. These constraints limit ATC's ability to move power in and out of the Upper Peninsula, and cause overloading on other parts of the electric system. To address the reliability problems, ATC is proposing a new 50-mile transmission line from the Morgan Substation south of Oconto Falls to a new substation - called Werner West - in the New London area.

Planning Engineer., SAIPEM CONTRACTING ALGERIE, Multiple Projects / Petrochemical ; Oil and Gas / EPC Project Controls

START Date: 
December, 2005

 

Summary of Experience

Company                   :  Saipem Contracting Algerie S.p.a.

Client                          : Sonatrach GNL3Z Project (LNG Project)

Location                     : Arzew, Algeria

Market Place