Lead Planner, Grinaker-LTA M&E, Taggart LSL Consulting Engineers, Kalagadi, Acrylic Acids and Acrylates Project (AAA), Mondi, Sishen Expansion Project

START Date: 
January, 2002
END Date: 
August, 2011

Senior planner in the engineering sector for materials handing to the mining industry. Previous experience includes lead planner to the construction industry (mining) relating to civils, structural steel, mechanical & platework, piping, electricals & instrumentation.

Planner, O & G Solutions, COEP - Cooper Oil Exploration Project

START Date: 
May, 2008
END Date: 
April, 2009

Worked with O & G Solution - JV between leading global EPCM company Aker Solutions and United Group – Provides integrated EPC and Operations and Maintenance services to Santos for existing Brownfield site in the Cooper Basin and Port Bonython Oil and Gas processing Plant with a contract value of A$20-40 million per annum

Project Objective was to eliminate Port Bonython and Moomba Oil & Gas plant bottleneck areas to increase plant output capacity.
 
Project scope includes following :
Moomba Site

Graduate planner, Balfour Beatty Management/Heery International, Various

START Date: 
August, 2007
END Date: 
April, 2010

 During this period, I was attending various software and personal development courses. My role was analysing the programme status, coding, structure, relationship links and merging of two or more programmes. This is done using primavera P6, MS project, MS excel and reporting the results back to the client. Once I had proved I had an increased understanding of the software I was sent to various sites to assist senior planners.My work involvedupdating and amending changes into the programme, producinga completion strategy drawing and created a programme for the completion.

Assistant Planner, Parsons Brinckerhoff, Airport heathrow

START Date: 
May, 2010

Project:    T2B (London Heathrow Terminal 2)

My position has covered a wide range of areas from producing a Detailed Programme covering Design, Procurement, Manufacture and Assembly for all works disciplines.  Also update the programme, attend all the technical, co-ordination and progress update meetings.

I developed programme in close contact with the engineers and project managers. In addition I work with the projects controls team and extract cost information from the programme for EV and other analysis.

Senior Planner, Parsons Brinckerhoff, Various

START Date: 
December, 2011

Senior planner for Parsons Brinkerhoff working on various mining projects.

Field Investigation Engineer, Aboitizpower Corp, Hydro-power Development

START Date: 
February, 2005

As Field Investigation Engineer - I make sure that the comprehensive requirement for the Design Group shall be met by leading various groups for site exploration and investigation such as survey, geological and geotechnical works. 

Sr Project control executive, Lauren CCLengineers india pvt ltd, 50 Mw solar power plant India

START Date: 
June, 2011

At present working as Sr Project control Executive for 50 Mw solar power project (CSP) in India.

My duties are:

1. Review and creck the schedule.

2. monitoring the progress of critical activities.

3.tracking the project for cost and time.

planning and project control manager, PT. Tripatra Engineers and Constructors, Concept, FEED, Detail Engineering & Procurement Services for Offshore Platform, Pipeline & Onshore Plant

START Date: 
April, 1996

More than fifteen (15) years experience in Project Management, Construction Management, Project Scheduling, Cost Control and Project Reporting for Engineering Procurement Construction Commissioning Project (EPCC) and Engineering Project. The experience includes: Prepared of Master, Detailed and Integrated EPCC schedules. Prepared of manpower planning for Engineering, Procurement, Construction, and Pre-commissioning / Commissioning. Projected completion dates and monitored progress toward milestones.

Planner & Coordinator, Hertel (UK) Ltd, Linsdey Oil Refinery Major Turnaround

START Date: 
April, 2011
END Date: 
August, 2011

I was responsible for the scheduling of a major outage on linsdey oil refinery for hertel uk ltd, my duties included

  • Scheduling Scaffolding & Insulation works
  • Progress Reporting
  • Productivity Factors

Planning Manager, Kaefer C&D, Killingholme M2 Major Outage

START Date: 
November, 2011
END Date: 
December, 2011

Planning Manager on a Major outage at Killingholme Powerstation, for Scaffolding, Insulation & Mechanical

I am responsible for

  • Creating pretender and work schedules
  • Productivity Factors
  • Risk Management
  • Resourse Management
  • Document Management
  • Updating and Publishing the Project Status Report.