On Offshore Gas Turbine Generator Set Project, I joint on mid of construction work. The project scope is to decommissioning the existing generator set and to construct 4 set new Gas Turbine Generator System complete with panel control set. The obstacle is limited space and no stop oil and gas production operation.
To solve problem limited space, we choose the GTG with big capacity and small size. For no stop production operation, we use external power plant that we set up the generator set on the barge with subsea cable. That condition will make the problem if the weather is bad.
Project Controls Lead. Build and enable a decision-making tool to manage all water projects (full cycle) under MODON scope. Create a comprehensive interactive database to facilitate planning and control of all water projects (from pre-concept to design, detailed design, construction, commissioning. including tendering). Validate MODON water consumption standards with actual data from sites. Establish progress and status visibility of all project interdependencies.
1. Manage tender process, prepare preconstruction documents such as but not limited to project execution plan (PEP), construction document audit review, and liaising with contractor and supervision consultant during construction stage
2. project management activities during construction
Responsibilities:Main role as Construction Manager in EPC contract
ProjectBrief:
Jordan Research and Training Reactor (JRTR) project is a multi-purpose open-pool type reactor.
JRTR is a five MW thermal research and test reactor, and it is being built by the Korean KAERI/DAEWOO consortium company (KDC), at the Jordan University for Science and Technology (JUST).
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.