/ Construction Project Planner / Senior Planner / Forensic Analyst, Pertamina EP, Offshore Power Plant
On Offshore Gas Turbine Generator Set Project, I joint on mid of construction work. The project scope is to decommissioning the existing generator set and to construct 4 set new Gas Turbine Generator System complete with panel control set. The obstacle is limited space and no stop oil and gas production operation.
To solve problem limited space, we choose the GTG with big capacity and small size. For no stop production operation, we use external power plant that we set up the generator set on the barge with subsea cable. That condition will make the problem if the weather is bad.
The project commissioning is late about 3 months because of bad weather. The target commissioning should done on september 2017 but the team can finish on december 2017.