Planning Team Leader

Planning Team Leader, Mott MacDonald Ltd., South East Electricity Substations Alliance

START Date: 
August, 2011

Current Role:

Planning Team Leader for SEESA (South East Electricity Substation Alliance - JV of National Grid, Mott MacDonald, Skanska and Alstom)

Team consists of 13 planners and senior planners.

Roles and Responsibilites include:

1. Team development, time keeping and work allocation.

2. Responsibility and accountability for the quality of output from the SEESA planning team

3. Peer Reviews to analyse plan integrity and compliance of planners

4.

Planning Team Leader, Cubic Transportation Systems Limited, Prestige Project (Oyster Smartcard System for London)

START Date: 
September, 1998
END Date: 
March, 2005

Planning Team Leader

Cubic Transportation Systems Ltd. (1998 – 2005)

Employed by Cubic, at Contract Award in September 1998, to work on the Prestige project as part of the TranSys consortium (Cubic, EDS, ICL and WS Atkins). The project involved the design and supply of the ‘Oyster’ contactless smartcard system for London covering tube, trains, buses and trams over a 17-year franchise period. The project was, at the time, the largest PFI contract in the UK transport sector. Responsibilities included:

Planning Team Leader, Aker Kvaerner, Multiple EPC Projects

START Date: 
August, 1996
END Date: 
September, 2004

Responsible for all planning within the organisation, supervising the planning department both internally and on all projects.  Also responsible for the recruitment of planning personnel, the development of corporate procedures and a member of the steering group responsible for the development of the Aker Kvaerner Integrated Management System (AKiMS).

Planning Team Leader, Mott MacDonald, South East Electricity Substations Alliance

START Date: 
October, 2008
END Date: 
June, 2010
National Grid South East Electricity Substations Alliance (SEESA) - Planning team leader for a team of planning engineers based in SEESA HQ, Stokenchurch. Responsible for day to day team management, periodic team peer reviews, ownership of the alliance planning process, Primavera database administrator, full lifecycle planning, earned value analysis and reporting and portfolio planning (including ‘what if’ scenario planning). Deputise for the Planning Manager to provide ongoing cover for leave periods.

Planning Team Leader, BP AzSPU, Marine

START Date: 
January, 2009
END Date: 
June, 2009
BP, Marine Operations Group

•Developing and maintaining the integrated Master Schedule for the Marine Operations Group.
•Responsible for overseeing development of the detailed level 4 schedules for Marine and Underwater Operations.
•Responsible for liaising with other AzSPU groups to ensure interfaces are managed and the latest information is incorporated into the overall Marine Operations Group schedule (drilling, marine, Major Projects, etc).

Planning Team Leader, Rolls Royce PLC, Various

START Date: 
June, 1988

Team Leader for Rolls-Royce Planning Team and Subject Matter Expert

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
Syndicate content