Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Consultancy Project Controls Engineer

Consultancy Project Controls Engineer, Gardiner & Theobald, Ellipta Phase 4

START Date: 
January, 2017
END Date: 
December, 2017

 

·        Subcontracted to GSK, Project Controls Ellipta Respiratory drug development.

·        Project scheduling using Microsoft project and Primavera Rel 16.1.

·        Pharmaceutical product planning of civil structure and management of factory equipment.

Experience Hours (Cost Management): 
0

Consultancy Project Controls Engineer, Gardiner & Theobald, Ellipta Phase 4

START Date: 
January, 2017
END Date: 
December, 2017

 

·        Subcontracted to GSK, Project Controls Ellipta Respiratory drug development.

·        Project scheduling using Microsoft project and Primavera Rel 16.1.

·        Pharmaceutical product planning of civil structure and management of factory equipment.

Consultancy Project Controls Engineer, AECOM, Commercial, Highway, Industrial, Residential, Transit, tunnel and airport construction

START Date: 
March, 1999
  • Sound Transit Central Link Light Rail, Beacon Hill Tunnel, Seattle, WA ($310 million) Served as Scheduler on the construction of a twin bore 21’ diameter, one-mile long light rail tunnel, associated trackwork and two transit stations. Reviewed and approved contractor CPM Schedule baseline and update submittals for completeness, accuracy and contract compliance. Prepared critical construction progress trend and status reports, responded to contractor delay claims, prepared Time Impact Analysis and as-built schedules. Prepared cost estimates for change orders.
Experience Hours (Planning & Scheduling): 
18000
Experience Hours (Cost Management): 
6000
Experience Hours (Forensic Analysis): 
8000

Consultancy Project Controls Engineer, NR, Railway civils, M&E, Resignalling

START Date: 
March, 1997

Integrated Planning & Control for all planner withing my company.

Consultancy Project Controls Engineer, FREE LANCER, Several Projects - Infrastructure -Housing

START Date: 
October, 2010

Project Mnagement- Schedulling- Planning- P6- Construction Law- Commercial Contracts- Cost Control

Consultancy Project Controls Engineer, AECOM, Libya mega infrastructure program

START Date: 
December, 2008
END Date: 
October, 2010

 

Project Controls Professional with over eight years of experience in the construction industry with government and international organizations. Certified Associate Value Specialist with expertise in project management, monitoring and controlling of infrastructure, housing, and power plants. Expertise with large-scale projects with budgets of $100M to $50B. Experience in planning and scheduling, specifically schedule and cost control and analysis. 

Consultancy Project Controls Engineer, ILF Consulting Engineers, Beineu - Bozoy- Shymkent Gas Pipeline Project

START Date: 
June, 2016

Project control Engineer : Gas Pipeline Project with one Metering Station, two Compressor Stations, 1450 km x 42“ Pipeline & BVS, SVS, PTS, CS.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content