CONSTRUCTION MANAGER, Parsons Brinckerhoff, Chiswell Street Hotel

START Date: 
December, 2007
END Date: 
September, 2008

Construction Manager – Chiswell Street Hotel (December 2007 – September 2008):

This was a £25m project with a construction management procurement process, involving the refurbishment of a 250 year Grade 2 listed old brewery building into a 215 bedroom hotel with spa, meeting rooms, bars, and other facilities. Involvement included the following: management of the site setup, multi-service gang, the internal fabric repair and dry-lining trade contractors.

CONSTRUCTION MANAGER, Sunpower Corporation, Solar parks

START Date: 
November, 2011

Main tasks

On site coordination and supervision of civil, mechanical and electrical works including plant commissioning, evacuation line, grid connection, SCADA and security system implementation, acceptance tests.

Subcontractor management, quality control, scheduling and accounting.

Support to Project Manager on negotiation with subcontractors, purchase orders, cash flow analysis, documentation management, verification of contractual obligations.

Project punch list closure, claim management, troubleshooting and handover to Client and O&M.

 

Construction Manager, Designer, Head of Estimating Department, Planning Engineer, Senior Cost Estimator, Senior Scheduler, Project Manager, Coleman Construction Corporation, Multiple projects across multiple sectors

START Date: 
June, 1983
END Date: 
December, 1986

Coleman Construction Corporation, Chief Estimator, Senior Scheduler, and Senior Project Manager, Virginia Beach, Virginia

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
4000

CONSTRUCTION MANAGER, Consultant, Expert Witness., Schedule Analyst, Senior Cost Estimator, Senior Scheduler, Senior Planner, Carson Construction, Multiple Projects

START Date: 
September, 1977
END Date: 
March, 1980

Carson Construction Corporation, Owner, Charlottesville, VA

Provided cost estimating and planning/scheduling services on a consultant basis, working with other contractors and owners.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1000

Manager of Construction Department, Charlottesville Lumber Company/Better Living, Multiple Projects

START Date: 
May, 1974
END Date: 
August, 1977

Charlottesville Lumber Company/Better Living, Building Contractor, Manager of Construction Department , Charlottesville, Virginia, 

Oversaw all field operations, including layout of work, scheduling of manpower, ordering materials and equipment and scheduling deliveries.  Studied, set up and maintained safety program, working with O.S.H.A inspectors and regulations. Coordinated subcontractors, in-house construction staff, negotiated contracts, took-off and estimated work, wrote scopes of work, provided p

Construction Manager, Harry Peers Steelwork, Longannet Power Station - FGD

START Date: 
January, 2008
END Date: 
February, 2008

Construction Manager for Harry Peers Steelwork on FGD Project at Longannet Power Station, Scotland.

CONSTRUCTION MANAGER, FLUXYS, FLUXYS LNG PROJECT

START Date: 
January, 2010
END Date: 
December, 2010

Within the context of the LNG reinforcement pipeline’s construction, management of the bypass and interruption stations erection:

• Review and follow-up of the planning and the main subcontractor activities using PRIMAVERA P6 EPPM;

• Management of the site meetings;

• Follow-up of the HSE Portofolio of 7 stations projects.

CONSTRUCTION MANAGER, Nasa Multiplex, Towers & High Rise Buildings

START Date: 
February, 1998
END Date: 
May, 2001

•Define the strategy for projects construction including establishing the cranage plans, the storage areas, and the movement of materials
•Evaluate the method statements and schedules of the subcontractors and their on site requirements, and include it in the Master CPM schedule
•Develop the overall working programme
•Coordinate with all parties to ensure compliance with the project master programme and the package master programme and to develop recovery programmes when required
 