Area Planning Engineer

Area Planning Engineer, ORIENT Energy System (Pvt.) Limited (OES), Construction of THATTA POWER PLANT, DADU POWER PLANT, OMNI POWER PLANT

START Date: 
January, 2010
END Date: 
December, 2012
  1. Develop, review and maintain the project plans and baseline schedules using Primavera
  2. Monitor progress throughout the construction process on a weekly basis and compare with work plan (Actual vs Baseline Schedule)
  3. Identify and review regularly, critical and sub-critical activities and monitor its impact on overall plan
  4. Develop and maintain project change control and review scope change requests for impact on schedules and the critical path of the project.
  5. Submitting planning package with all allied documents
  6. Ensuring availability of drawings in l
Experience Hours (Planning & Scheduling): 
4900
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
50

Area Planning Engineer, PetroSA (PTY) Ltd, Refinery Shutdown

START Date: 
November, 2009
END Date: 
December, 2014
  • Shutdown And Turnaround Planning And Execution (Implementing 7 Phases Planning Cycle).

 

  • Compilation of Shutdown and Turnaround Schedules (Bar Charts Using Primavera And Or Ms Projects.

 

  • Originate And Review Planning And Scheduling Documentation.

 

  • Facilitation the Execution of Shutdown and Turnaround Plans and Schedules.
  • Reporting and Continuous Improvement of Maintenance Kpi’s.

 

  • Provide Guidance To Formulation Of Long Term Outage Plan.

 

Experience Hours (Planning & Scheduling): 
10400
Experience Hours (Cost Management): 
1400

Area Planning Engineer, VCS Quality Services Pvt. Ltd., DNEPL Project

START Date: 
October, 2015
END Date: 
May, 2018
  • PMC services of Overall Cross-Country Pipe Line to Reliance Gas Pipelines Ltd. (India), for EPC Dhaej Nagothane Ethane Pipeline (DNEPL) consist of pipeline of 12 inch and combined length of 480 Kms.
Experience Hours (Planning & Scheduling): 
10800
Experience Hours (Cost Management): 
900
Experience Hours (Forensic Analysis): 
50

Area Planning Engineer, KALPATARU POWER TRANSMISSION lIMITED, PRP-AMD

START Date: 
December, 2013
END Date: 
September, 2015
  • Engineering, Procurement & Construction Services of Cross Country Pipe Line to Oil & Natural Gas Corporation Ltd. (ONGC) India, for Pipeline Replacement Project of Ahmedabad Assets (PRP-AMD), consist of pipeline of 4, 6, 8, 12, & 14 inch and combined length of 248 Kms.
Experience Hours (Planning & Scheduling): 
3400
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
0

Area Planning Engineer, Sicim Kazakhstan, FGP /WPMP

START Date: 
February, 2017

Ø  Main scope includes Engineering, Procurement and Construction work (Temporary facilities, Civil, UG Piping, Electrical, Instrument and Pre-Commissioning).

Ø  Able to understand the Technical Scope of work, Scheduling / Planning the appropriate set of activities and ensuring on timely completion of Project by Operating  Primavera Software.

Ø  Developing of EPC Master Schedule using Primavera P6 Software and updates on weekly basis.

Area Planning Engineer, Orascom, Talkha Power Station

START Date: 
June, 2005
END Date: 
December, 2009

• Preparing bid schedules for all projects in the bidding stage. • 
• Preparing baseline schedules for all awarded projects.

Area Planning Engineer, Various - most are now out of business, (various projects)

START Date: 
July, 1994
END Date: 
December, 2000

Working as Project Control/Planning on various refinery and petrochemical plants

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
5000

Area Planning Engineer, Network Rail Ltd, Southern Power Supply Upgrade Project

START Date: 
January, 2003
END Date: 
November, 2003

A member of Network Rail Southern Region Power Upgrade Project, resposible for the development of programmes to support HMRI Railway Safety Regulations were met regarding the replacement of Mark 1 Slam Door Trains.

Experience Hours (Planning & Scheduling): 
1750
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
0

Area Planning Engineer, TCO, FGP/WPMP

START Date: 
October, 2015

Working on the Engineering side of the Future Growth Project (FGP) in the areas of Brownfield, Overhead Power Distribution (OHPD), Fibre Optic Backbone (FOB) and Tie-ins. My role for the client (TCO) involves closely monitoring the KPJV planning element along with other specialist contractors involved with the Engineering aspect of the project. I am also a focal point between Engineering and Construction (for my areas)....

Experience Hours (Planning & Scheduling): 
1550

Area Planning Engineer, Maaga Engineering, & Oil & Gas Projects

START Date: 
May, 2016

Hello, 

this is a very usefull website for planners and it will help to improve our knowledge...

thank you

Experience Hours (Planning & Scheduling): 
300
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
150