Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Area Planning Engineer

Area Planning Engineer., Foster Wheeler, Ras Tanura Integrated Project

START Date: 
January, 2010
END Date: 
January, 2011

 

Area Planning Engineer., Al Jaber Building L.L.C, Villas and Low Rise Buildings Construction

START Date: 
June, 2007

Since 2007 I'm working as a planning engineer in the United Arab Emirates for a main contractor reporting directly to the project director.

Tender Schedules preparation.

Developing baseline schedules (Resources and cost loaded) using P3, P6 V7

Updating baseline and progress reporting.

Preparing recovery and action plans.

Extension of Time.

 

Involved in two mega projects (Al Raha Garden >>"1400 Villas" & Al Falah Community Development >>"2080 Villas") and many other small resedential projects.

Area Planning Engineer., Al Jaber Building L.L.C, Villas and Low Rise Buildings Construction

START Date: 
June, 2007

Since 2007 I'm working as a planning engineer in the United Arab Emirates for a main contractor reporting directly to the project director.

Tender Schedules preparation.

Developing baseline schedules (Resources and cost loaded) using P3, P6 V7

Updating baseline and progress reporting.

Preparing recovery and action plans.

Extension of Time.

 

Involved in two mega projects (Al Raha Garden >>"1400 Villas" & Al Falah Community Development >>"2080 Villas") and many other small resedential projects.

Area Planning Engineer., Bouygues Batiment International – QATAR, OFFICE BUILDINGS

START Date: 
April, 2011

§  Responsible include Planning, Scheduling & Monitoring of MEP works through Primavera

§  Developing process to ensure that all work done for the client meets the agreed quality norms & is delivered according to the set deadlines

§  Preparation & documentation of running bills. Progress Report, Cash Flow Chart

§  To provide single interface to Planning, Design & Construction integration

Area Planning Engineer., "Mohammad Al Mojil Group ( Jubail City, K.S.A)", Saudi Kayan Petrochemical Complex

START Date: 
December, 2006
END Date: 
March, 2008

SHARQ 3rd Expansion Project
Off site expansion control and planning, ARAMCO standards reflection and time delay and qualified work groups and personnel. (Under MMG)

Saudi-Kayan Petrochemical complex erection
Area 21 (Off Plot) : Pipe line Planning including Port Area Tank Farm Civil work Planning.
Area 22 (Modularization): Structural Work Modularization and Pipe Rack Erection.

Area Planning Engineer, RIPI(Research Institute of Petroleum Industry), GTL

START Date: 
July, 2003
END Date: 
December, 2004

It was my first exprince and our project was a Research project

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content