Area Planning Engineer

Area Planning Engineer, Ltd., Siemens Pakistan Engg Co, Islamabad, New Benazir Bhutto International Airport Project, PAKISTAN

START Date: 
May, 2009

 

Work experience:-    (May 2009 to till date)

May 2012 to till Date

Company:              Siemens Pakistan Engineering Co. Ltd.

Project Location:      New Benazir Bhutto International Airport Islamabad

Project Title:             

Area Planning Engineer, PBAD.SBG -Saudi Binladn Group, Public Sevice Centre. Jeddah

START Date: 
February, 2013
END Date: 
September, 2013

 

I am  a PMI certified Professional working in construction industry for more than a decade.My responsibilities are risk Management,Project Planning and scheduling, Cost Control ,Testing and Commissioning and Close out of Projects.

Area Planning Engineer, SOJV - Taisei Corp - TAV, Airport (Doha), (2) 3B+G+14 Stories+ Swimming Pool (Office & Residential) Building

START Date: 
April, 2007

 

v  Prepare Tender Preliminary schedule including Project Codes, Activity Codes and WBS Codes

v  Prepare detail Baseline Construction Schedule incorporating all the aspects of works from Engineering, Procurement, Mobilization, Construction, Fabrication, Installation and Turn-over

v  Prepare Histograms, S‐Curves, Cost/ Resource Loading and Look‐ahead Schedules which include the design and forecasting of accomplishment to meet the target milestone.

Area Planning Engineer, SOJV - Taisei Corp - TAV, Airport (Doha), (2) 3B+G+14 Stories+ Swimming Pool (Office & Residential) Building

START Date: 
April, 2007

 

v  Prepare Tender Preliminary schedule including Project Codes, Activity Codes and WBS Codes

v  Prepare detail Baseline Construction Schedule incorporating all the aspects of works from Engineering, Procurement, Mobilization, Construction, Fabrication, Installation and Turn-over

v  Prepare Histograms, S‐Curves, Cost/ Resource Loading and Look‐ahead Schedules which include the design and forecasting of accomplishment to meet the target milestone.

Area Planning Engineer, DAR AL OMRAN, Water & Wastewater Project

START Date: 
September, 2010
END Date: 
September, 2013

1- Maintain Master Schedule 

2- Monthly Update for the Baseline Schedule 

3- S- Curve 

4- Comparison Between the baseline and the Update 

5- EVM 

Area Planning Engineer, Taylor Woodrow (Civl Engineering Divison of Vinci UK), NET Phase Two

START Date: 
August, 2001

  

Responsible for most critical areas of the project, work with Project/section Managers to develop project programme with knowledge of critical path, float and risk & opportunity.

Understanding the key requirements of the Works Information and the programme obligations required under the contract.

Area Planning Engineer, SACCAL HOLDING, LAUPDC PROJECT

START Date: 
September, 2004

·        Over 9 years'experience.

·        Project management.

·        Earned Value Management.

·        Unique combination of Technical and Management skills.

·        Team builder with motivational skills.

Area Planning Engineer, SACCAL HOLDING, LAUPDC PROJECT

START Date: 
September, 2004

·        Over 9 years'experience.

·        Project management.

·        Earned Value Management.

·        Unique combination of Technical and Management skills.

·        Team builder with motivational skills.

Area Planning Engineer, ARAMCO SRACO COMPANY, KARAN GAS PLANT PROJECT

START Date: 
April, 1989

<?xml:namespace prefix = v />

Area Planning Engineer, ARAMCO SRACO COMPANY, KARAN GAS PLANT PROJECT

START Date: 
April, 1989