Area Planning Engineer

Area Planning Engineer, Petrofac Engineering Construction, laggan tormore

START Date: 
December, 2013

Name:                  LEWIS WALKER REEVES

 

Address:               45 Knockrivoch Place

     Ardrossan

     Ayrshire

 

     KA22 7PY 

 

Home Tel:            01294 466815

Mobile Tel:   &nbsp

Experience Hours (Planning & Scheduling): 
12000

Area Planning Engineer, Ayala Land Corporation, Ayala Life Satellite Office

START Date: 
March, 1997
END Date: 
December, 1997

Ayala Land Corporation

Location:Philippines

Project: Ayala Life satellite offices

Date Join: March 1997 – December 1997

Planning Engineer

§  Working as part of the Construction Department

§  Duties include planning, managing and controlling cost resources.

§  Strategic analysis of Whole life Asset Management for Construction Department.

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
1500

Area Planning Engineer, Aveon, Offshore Platform

START Date: 
February, 2014

Position: Planning Engineer                                                               Feb 2014 to Till Now

 

Area Planning Engineer, MASCO, Haramain High Speed Railway Project

START Date: 
February, 2012
  • Prepare and maintain detailed schedules for project including development of critical path and project float.
  • Preparing progress sheets is shown project status per (Week- month-Year).
  • Preparing S-Curves for cash in, cash out, man power and Equipments.
  • Preparing Monthly Report including all further details about the project status.
  • Estimating sub-contractors work and their performance.
  • Preparing recovery plan in case of any delay.
  • Preparing Monthly invoices.

Preparing prequalification documents and Tenders for new Projects.&nbs

Area Planning Engineer, MASCO, Haramain High Speed Railway Project

START Date: 
February, 2012
  • Prepare and maintain detailed schedules for project including development of critical path and project float.
  • Preparing progress sheets is shown project status per (Week- month-Year).
  • Preparing S-Curves for cash in, cash out, man power and Equipments.
  • Preparing Monthly Report including all further details about the project status.
  • Estimating sub-contractors work and their performance.
  • Preparing recovery plan in case of any delay.
  • Preparing Monthly invoices.

Preparing prequalification documents and Tenders for new Projects.&nbs

Area Planning Engineer, Al Latifia Trading & Contracting Co., Hilton Riyadh Hotel & Residence

START Date: 
March, 2011
END Date: 
January, 2014

·Experienced in planning and coordinating upstream developmental construction activities.

·Providing site team with the required look ahead schedule and progress update in order to meet the project schedule and planned progress milestones.

·Providing the site team with various daily, weekly and monthly reports along with activity monitoring sheets and progress charts.

·Conduct and coordinate progress meetings and coordination meetings along with client, main contractor,

Area Planning Engineer, Hyundai Arabia, Power Plant

START Date: 
January, 2014

Planning Engineer at Hyundai Arabia Company, newly Joined the Company

Area Planning Engineer, Hyundai Arabia, Power Plant

START Date: 
January, 2014

Planning Engineer at Hyundai Arabia Company, newly Joined the Company

Area Planning Engineer, Hyundai Arabia, Power Plant

START Date: 
January, 2014

Planning Engineer at Hyundai Arabia Company, newly Joined the Company

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.