Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

%100 Project Planning; Budgeting; Project Control; Risk Analysis; Resource allocation

/ Construction Project Planner / Senior Planner, Worley, Koodaideri Mine to Port transfer project

START Date: 
August, 2019
END Date: 
February, 2021

Accommodation Forecasting

Procurement Statussing

NPI Schedule analysis and Reporting on Contractor Works

Critical Path Indentification & Analysis

Experience Hours (Planning & Scheduling): 
1800
Experience Hours (Forensic Analysis): 
400

Project Manager, Axioma Proyectos, Warehouse

START Date: 
October, 2019
END Date: 
May, 2020

Project Manager: Responsible in Planning and Scheduling deliverables in compliance to the owner requirements.

Experience Hours (Planning & Scheduling): 
600
Experience Hours (Cost Management): 
600

/ Construction Project Planner / Senior Planner, Hexagon, MEGPL

START Date: 
June, 2015
END Date: 
June, 2020
Project Services & Controls Specialist Oversee project planning team tasked with scoping capital and turnaround projects from concept to delivery; strategize and implement end-to-end Work Breakdown Structure, including all work packs. Conduct feasibility assessments for onshore and offshore engineering designs. Advise and approve construction project materials including mechanical and electrical instrumentation and equipment.
Experience Hours (Planning & Scheduling): 
7500
Experience Hours (Cost Management): 
7500
Experience Hours (Forensic Analysis): 
7500

Planning and Project Control Lead , Ine-Parsons, Oil, Gas and Petrochemical Projects in South America

START Date: 
June, 1993
END Date: 
March, 2001

Leading the planning and project control function for the assigned proposal and/or project  

Divisional Director Project Controls, TfNSW, $16 billion regional program including major transport and maritime infrastructures

START Date: 
August, 2017
END Date: 
July, 2018

Responsible for leading the planning and project controls function for the $16 billion regional program including major transport and maritime infrastructures • led and coordinated the project assurance function, in line with INSW and TfNSW requirements • ensured efficient and effective monitoring and management of the project office’s project controls and support compliance and assurance activities • coordinated audit programs and requirements for the Project Management Office, across financial and non-financial disciplines

/ Construction Project Planner / Senior Planner, Bouygues E&S UK Ltd, Data Centers

START Date: 
May, 2018
Bouygues Energies & Services Contracting, London Project Planner, May 2018 to Present Formulate a pre-construction/construction, commissioning programme and a methodology at tender stage. Create fully resource loaded and baselined project programmes for major phases of the project, including design, installation and commissioning, milestones capturing key dates, and client deliverables, based on agreed WBS.
Experience Hours (Planning & Scheduling): 
17300
Experience Hours (Cost Management): 
10550
Experience Hours (Forensic Analysis): 
800

/ Construction Project Planner / Senior Planner, Bouygues E&S UK Ltd, Data Centers

START Date: 
May, 2018
Bouygues Energies & Services Contracting, London Project Planner, May 2018 to Present Formulate a pre-construction/construction, commissioning programme and a methodology at tender stage. Create fully resource loaded and baselined project programmes for major phases of the project, including design, installation and commissioning, milestones capturing key dates, and client deliverables, based on agreed WBS.
Experience Hours (Planning & Scheduling): 
17300
Experience Hours (Cost Management): 
10550
Experience Hours (Forensic Analysis): 
800

/ Construction Project Planner / Senior Planner, Bouygues E&S UK Ltd, Data Centers

START Date: 
May, 2018
Bouygues Energies & Services Contracting, London Project Planner, May 2018 to Present Formulate a pre-construction/construction, commissioning programme and a methodology at tender stage. Create fully resource loaded and baselined project programmes for major phases of the project, including design, installation and commissioning, milestones capturing key dates, and client deliverables, based on agreed WBS.
Experience Hours (Planning & Scheduling): 
17300
Experience Hours (Cost Management): 
10550
Experience Hours (Forensic Analysis): 
800

/ Construction Project Planner / Senior Planner, Bouygues E&S UK Ltd, Data Centers

START Date: 
May, 2018
Bouygues Energies & Services Contracting, London Project Planner, May 2018 to Present Formulate a pre-construction/construction, commissioning programme and a methodology at tender stage. Create fully resource loaded and baselined project programmes for major phases of the project, including design, installation and commissioning, milestones capturing key dates, and client deliverables, based on agreed WBS.
Experience Hours (Planning & Scheduling): 
17300
Experience Hours (Cost Management): 
10550
Experience Hours (Forensic Analysis): 
800

Project Controls Specialist, Ausenco, Mina Justa

START Date: 
October, 2017
END Date: 
August, 2018
Project Controls
Experience Hours (Planning & Scheduling): 
1650
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content