Asta Powerproject

Setting a start date

Good morning,

Might be a noobie question but I am fairly new to Asta.

I am wondering how to set a line to start on a certain date and not follow the logic.

To put it in context, we can have the gas connection completed after we have removed scaffold but the gas company are booked in for 2 weeks after the scaffold. So the logic on my programme says it will happen right after the scaffold is gone, but I want it to say it is happening 2 weeks after. So when I reschedule it brings it back to after the scaffold.

 

Copying Custom Calendar between projects

I created a custom calendar for one project and want to use the same calendar for another project.  How do I copy it from one project to another?

Jeff

As Planned Vs As built - Comparison

Good morning, 

I am looking to compare the as built with the as planned - Is it possible to export this in some format into excel to compare variances in duarations? Or is there an easy way to compare i.e. Planned 5 days, As built 10 days?

Thanks in advance, 

Dominic 

Text Annotations on Bar Chart

Greetings Planners,

I have recently changed over from Primavera to Asta Powerproject and I am strugling to move my auto-Text Annotations to be centered and above each bar on my bar chart....left and right is no problem but centered and above is proving difficult....

Any assistance is welcomed....

Thanks in advance,

Darren

Display Options

Hi All, 

I need some assistance in regards to displaying a two weekly programme. 

Firstly, I have all non-working time showing but with a grey fill, how can this be made to go behind the subheadings?

Secondy, is there a way to specify a time period to be printed? I've managed to only have the tasks within a timesheet showing with a filter however when I go to print it seems to be fixed on printed 3-4 months as opposed to 3-4 weeks. 

Thanks for your help. 

Comparing Baselines and finish variance

Hi,

I have created a programme and created baseline(1) then shown impact of delays by rescheduling and created a further baseline (2)

I have then added further delays and rescheduled again to give the ovoerall delay.

I can find the overall delay by comparing live data to baseline (1) and displaying finish variance column howeverr I am looking to split the repsonibility of the delays. 

Is there a way you can show the finish variance between baseline (1) and (2) in one column and the overall finish variance in  another.

"Retain Logic" in ASTA

Hi,

I have to switch to ASTA from P6 due to my recent move and learning about ASTA everyday. I struggle to do the same thing in ASTA which I can do easily with P6 but I take it as a challange and happy to go for learning this new software.

My questions it is there any function called "Retain Logic" like P6 to maintain the logic alive for out of sequence items? So my task A-B-C are linked finish to start. if my item B is finished out of sequence and still A hasn't finished, why my item C is showing on the status date rather than start after item A?

Negative float applies to chain

I am fairly new to Asta Project Planner, I am troubled that the contractor has submitted a schedule indicating activities with remining durations indicate finish dates prior to the data date.

For example, one activity indicated a remaing duration of 10days; however, the activity was shown completing on September 27, 2017  or prior the progress date or data date of OCT 1, 2017.

Need help with Asta "logic"

I was born and raised with Primavera but recenlty started using Asta as well to broden my knowledgebase. The addaptaion has not been smoth and i struggle with the idea that Asta is somehow superior to P6. But maybe it's just my way of thinking that is at fault?

Here is an example i struggled with all day today. 

Asta Power Projects BIM module, model disappears in 3D pane

Good morning all

I am Dave from Interserve Construction in Swansea, quite new to Asta but have been using 3D software for 14 years now.

I have linked in an IFC file to my programme, all good, however, when I place a site componant such as a piece of hoarding I loose it on screen as it places itself miles from my building.

Then when I view the model the pane looks blank as the model is a small pixel somewhere in one corner and the hoarding is a pixel somewhere in the other corner.  Resetting the view doesnt help either.