Copying Custom Calendar between projects

2 replies [Last post]
Jeff Raykos
User offline. Last seen 6 years 13 weeks ago. Offline
Joined: 24 Jan 2018
Posts: 3
Groups: None

I created a custom calendar for one project and want to use the same calendar for another project.  How do I copy it from one project to another?

Jeff

Replies

Jeff Raykos
User offline. Last seen 6 years 13 weeks ago. Offline
Joined: 24 Jan 2018
Posts: 3
Groups: None

Thanks Mike.  I did try the copy and paste but maybe I wasn't doing it correctly.  I was able to copy a task, and paste it into the new schedule and it carried the calendar with it.

Thanks again!

Jeff

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jeff

Highlight and copy the calendar you want.

Go to the new project and copy the calendar.

If the calendar wizard pops up then disable it first.

Alternatively copy a single task and copy it into the new projoject and it should bring all the other objects with it for you to retain or de select.

Best regards

Mike T.