Text Annotations on Bar Chart

10 replies [Last post]
Darren Gregg
User offline. Last seen 3 years 4 days ago. Offline
Joined: 11 Dec 2017
Posts: 7

Greetings Planners,

I have recently changed over from Primavera to Asta Powerproject and I am strugling to move my auto-Text Annotations to be centered and above each bar on my bar chart....left and right is no problem but centered and above is proving difficult....

Any assistance is welcomed....

Thanks in advance,

Darren

Replies

karim farghaly
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Mike 

if i am planning to annotate the cost on bar chart during the 4d simulation

is there any way to make only one annotation and the cost changes during the simulation 

or 

to put annotation on each activity?

thanks

karim farghaly
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Mike 

if i am planning to annotate the cost on bar chart during the 4d simulation

is there any way to make only one annotation and the cost changes during the simulation 

or 

to put annotation on each activity?

thanks

karim farghaly
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Mike 

if i am planning to annotate the cost on bar chart during the 4d simulation

is there any way to make only one annotation and the cost changes during the simulation 

or 

to put annotation on each activity?

thanks

karim farghaly
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Mike 

if i am planning to annotate the cost on bar chart during the 4d simulation

is there any way to make only one annotation and the cost changes during the simulation 

or 

to put annotation on each activity?

thanks

karim farghaly
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Mike 

if i am planning to annotate the cost on bar chart during the 4d simulation

is there any way to make only one annotation and the cost changes during the simulation 

or 

to put annotation on each activity?

thanks

karim farghaly
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Mike 

if i am planning to annotate the cost on bar chart during the 4d simulation

is there any way to make only one annotation and the cost changes during the simulation 

or 

to put annotation on each activity?

thanks

karim farghaly
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Mike 

if i am planning to annotate the cost on bar chart during the 4d simulation

is there any way to make only one annotation and the cost changes during the simulation 

or 

to put annotation on each activity?

thanks

karim farghaly
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Mike 

if i am planning to annotate the cost on bar chart during the 4d simulation

is there any way to make only one annotation and the cost changes during the simulation 

or 

to put annotation on each activity?

thanks

Darren Gregg
User offline. Last seen 3 years 4 days ago. Offline
Joined: 11 Dec 2017
Posts: 7

Good stuff, thankyou, I'm sorted now.

Darren

Mike Testro
User offline. Last seen 8 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4407

Hi Daren

Welcome to planning planet and well done for chosing the best software.

To align the text box on the task just drag and drop the box onto the task where the arrows fall into the place you want.

You have to do it for each one but it is a simple task.

Best regards

Mike Testro