Asta Powerproject

Is there a way to link one file to another file?

Hi everyone,

Was wondering if it is possible to link one programme to a seperate programme (two seperate files)

For example if I have a Pre-Construction programme on one file and I would like to link it to a seperate file which contains the Construction programme.

How would I go about doing this? or is this not possible?

Hide Bar

Dear experts/Mike

Please mention the steps that 

1) How to hide bar under shaded timescale?

Prospective Forensic Analysis/Programme Audit/ Delay Analysis

I am dealing with  complex project that seems to be growing arms and legs and as such there has been slippages and delays to the programme. 

Can anyone give me advice on how best to analyse this? I would like to carry out some detailed analysis and to carry out some root cause analysis but not sure where to begin. 

Thanks!

Date Zone Properties-Adding project weeks

I am looking to add the project weeks to the top line in the date zone properties so that I can quickly see which weeks have elapsed. At present it is set to days. How do I amend this to weeks?

 

Thanks 

Delayed, but by how much?

Hi all, 

My project has delays and I want to quantify the delay. How do I do this, is it easy to do?

I would like to be able to put a figure forward, is there a report that can be used to demonstrate the delay?

Thanks 

Remove time in date format

HI,

 

I am trying to remove the time in the date format for barchart labels, does anyone can help me?

 

Regards,

Natalia

Fonts and Formatting

Greetings Planners, my first post so be gentle.

I have inherited a programme and I am unable to increase the fonts in each subheading that's been created. I have successfully managed to change all the other fonts in the activities and other headings but these are stuck at 5. This makes them to small to read when I print the programme off. I have tried using the fonts on the 'Home' tab to no avail, likewise using the 'Default Table Fonts' in the Format tab. Both of which weren't of any use. 

Any advice is appreciated.

Thanks, 

 

Dom

How do you change duration default to days?

Hello

I use Powerproject 12 and when I enter the duration for a task and hit enter it defaults to seconds. Is there a way to make the duration column default to days unless another unit is entered?

I've tried formating cells, catogory duration and the time unit day with out result.

Asta Powerproject SaaS - for Windows, Mac, tablets etc

Hi,

I've been asked on here and other forums about using Asta Powerproject on devices other than Windows PC, and also about having a cloud version so licences can be moved around freely.

Changing end date on progressed activity

I've just started using Asta PP after working on P6, and I'm a bit thrown by how you accomplish even simple things.

In P6 once I had marked the progress on an activity you could use the Anticipated end date to change the planned end date of a task, now this may be a dense question, but how do I do the equivilent in Asta?

If I try and change the finish date, it simply jumps back to the original finish, it won't accept the new date I'm giving it.

Thanks

 

h-angell